§5.2 FINAL PAYMENT <br /> §5.2.1 Final payment,constituting the entire unpaid balance of the Contract Sum,shall be made by the Owner to the <br /> Contractor when <br /> .1 the Contractor has fully performed the Contract except for the Contractor's responsibility to correct <br /> Work as provided in Section 12.2.2 of AIA Document A201-2007,and to satisfy other requirements, <br /> if any,which extend beyond final payment;and <br /> .2 a final Certificate for Payment has been issued by the Architect. <br /> §5.2.2 The Owner's final payment to the Contractor shall be made no later than 30 days after the issuance of the <br /> Architect's final Certificate for Payment,or as follows: <br /> ARTICLE 6 DISPUTE RESOLUTION <br /> §6.1 INITIAL DECISION MAKER <br /> The Architect will serve as Initial Decision Maker pursuant to Section 15.2 of AIA Document A201-2007,unless <br /> the parties appoint below another individual,not a party to this Agreement,to serve as Initial Decision Maker. <br /> (If the parties mutually agree, insert the name, address and other contact information of the Initial Decision Maker, <br /> if other than the Architect.) <br /> §6.2 BINDING DISPUTE RESOLUTION <br /> For any Claim subject to,but not resolved by,mediation pursuant to Section 15.3 of AIA Document A201-2007,the <br /> method of binding dispute resolution shall be as follows: <br /> (Check the appropriate box.If the Owner and Contractor do not select a method of binding dispute resolution <br /> below, or do not subsequently agree in writing to a binding dispute resolution method other than litigation, Claims <br /> will be resolved by litigation in a court of competent-jurisdiction) <br /> [ ] Arbitration pursuant to Section 15.4 of AIA Document A201-2007 <br /> [X] Litigation in a court of competent jurisdiction <br /> [ J Other(Specify) <br /> ARTICLE 7 TERMINATION OR SUSPENSION <br /> §7.1 The Contract may be terminated by the Owner or the Contractor as provided in Article 14 of AIA Document <br /> A201-2007. <br /> §7.2 The Work may be suspended by the Owner as provided in Article 14 of AIA Document A201-2007. <br /> ARTICLE 8 MISCELLANEOUS PROVISIONS <br /> §8.1 Where reference is made in this Agreement to a provision of AIA Document A201-2007 or another Contract <br /> Document,the reference refers to that provision as amended or supplemented by other provisions of the Contract <br /> Documents. <br /> §8.2 Payments due and unpaid under the Contract shall bear interest from the date payment is due at the rate stated <br /> below,or in the absence thereof,at the legal rate prevailing from time to time at the place where the Project is <br /> located. <br /> (Insert rate of interest agreed upon, if any.) <br /> AIA Document A101" —2007.Copyright©1915,1918,1925,1937,1951,1958,1961,1963,1967,1974,1977,1987,1991,1997 and 2007 by The American <br /> Init. Institute of Architects.All rights reserved.WARNING:This AIA®Document is protected by U.S.Copyright Law and International Treaties.Unauthorized 5 <br /> reproduction or distribution of this AIA®Document,or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to the <br /> i maximum extent possible under the law.This document was produced by AIA software at 11:09:21 on 08/21/2018 under Order No.8065734178 which <br /> expires on 04/11/2019,and is not for resale. <br /> User Notes: <br /> (389ADA20) <br />