Item Coversheet Page 2 of 2 <br /> Budget Impact: The final authorized contract amount of$89,504,535.96 is not changed by Change Order No 22. <br /> Staffing Impact: Staff time is allocated to manage the project. <br /> SCHEDULE: All dredging is complete,and demobilization is scheduled to be complete by December 31,2019. Final restoration <br /> of Oakley Sediment Basin site and other areas disturbed by the project will be completed by August 1,2020. <br /> COPY: Steve Lane-Great Lakes Dredge and Dock <br /> ATTACHMENTS: <br /> Description Type <br /> Resolution�vith Exhibits 2019-239 Resulutiun I.cltct• <br /> https://decatur.novusagenda.com/AgendaWeb/C�verSheet.aspx?ItemID=2571 12/16/2019 <br />