§ 9.4 Based on the Architect's observations and evaluations of the Contractor's Applications for Payment,the
<br /> Architect will review and certify the amounts due the Contractor.
<br /> § 9.5 The Architect has authority to reject Work that does not conform to the Contract Documents.
<br /> § 9.6 The Architect will promptly review and approve or take appropriate action upon Contractor's submittals,but
<br /> only for the limited purpose of checking for conformance with information given and the design concept expressed in
<br /> the Contract Documents.
<br /> § 9.7 On written request from either the Owner or Contractor,the Architect will promptly interpret and decide matters
<br /> concerning performance under,and requirements of,the Contract Documents.
<br /> § 9.8 Interpretations and decisions of the Architect will be consistent with the intent of,and reasonably inferable from
<br /> the Contract Documents,and will be in writing or in the form of drawings.When making such interpretations and
<br /> decisions,the Architect will endeavor to secure faithful performance by both Owner and Contractor,will not show
<br /> partiality to either and will not be liable for results of interpretations or decisions rendered in good faith.
<br /> § 9.9 The Architect's duties,responsibilities,and limits of authority as described in the Contract Documents shall not
<br /> be changed without written consent of the Owner,Contractor,and Architect.Consent shall not be unreasonably
<br /> withheld.
<br /> ARTICLE 10 CHANGES IN THE WORK
<br /> § 10.1 The Owner,without invalidating the Contract,may order changes in the Work within the general scope of the
<br /> Contract,consisting of additions,deletions or other revisions,and the Contract Sum and Contract Time shall be
<br /> adjusted accordingly,in writing.If the Owner and Contractor cannot agree to a change in the Contract Sum,the Owner
<br /> shall pay the Contractor its actual cost plus reasonable overhead and profit.
<br /> § 10.2 The Architect may authorize or order minor changes in the Work that are consistent with the intent of the
<br /> Contract Documents and do not involve an adjustment in the Contract Sum or an extension of the Contract Time.Such
<br /> authorization or order shall be in writing and shall be binding on the Owner and Contractor.The Contractor shall
<br /> proceed with such minor changes promptly.
<br /> § 10.3 If concealed or unknown physical conditions are encountered at the site that differ materially from those
<br /> indicated in the Contract Documents or from those conditions ordinarily found to exist,the Contract Sum and Contract
<br /> Time shall be subject to equitable adjustment.
<br /> ARTICLE 11 TIME
<br /> § 11.1 Time limits stated in the Contract Documents are of the essence of the Contract.
<br /> § 11.2 If the Contractor-is delayed at any time in progress of the Work by changes ordered in the Work,or by labor
<br /> disputes,fire,unusual delay in deliveries,unavoidable casualties,or other causes beyond the Contractor's control,the
<br /> Contract Time shall be subject to equitable adjustment.
<br /> § 11.3 Costs caused by delays or by improperly timed activities or defective construction shall be borne by the
<br /> responsible party.
<br /> ARTICLE 12 PAYMENTS AND COMPLETION
<br /> § 12.1 Contract Sum
<br /> The Contract Sum stated in this Agreement,including authorized adjustments,is the total amount payable by the
<br /> Owner to the Contractor for performance of the Work under the Contract Documents.
<br /> § 12.2 Applications for Payment
<br /> § 12.2,1 At least ten days before the date established for each progress payment,the Contractor shall submit to the
<br /> Architect an itemized Application for Payment for Work completed in accordance with the values stated in this
<br /> Agreement.The Application shall be supported by data substantiating the Contractor's right to payment as the Owner
<br /> or Architect may reasonably require,such as evidence of payments made to,and waivers of liens from,subcontractors and
<br /> Init. AIA Document A10511-2017.Copyright @ 1993,2007 and 2017The American Institute of Architects All rights reserved rhe /rr r rn-,;r,ct r i r.rc i;ects,"
<br /> _ .6 o c ., ,.rid „/,Cc mr;c.�crumr::, c r. c r ,<s ar nna co ,e:.sec r r . -�r i 'cn.This document was produced by $
<br /> AIA software at 14:12:48 ET on 02/01/2023 under Order No.2114398311 which expires on 01/10/2024,is not for resale,is licensed for one-lime use only,and may
<br /> only be used in accordance with the AIA Contract Documents®Terms of Service.To report copyright violations,e-mail copyright@aia.org.
<br /> User Notes: (1851015736)
<br />
|