Laserfiche WebLink
CITY OF DECATUR <br /> SUPPLEMENTAL SPECIFICATIONS <br /> SECTION 105. CONTROL OF WORK <br /> 105.07 Cooperation with Utilities. Revise the fourth paragraph of subparagraph(a)of this <br /> Article to read: <br /> "The Contractor shall be responsible for requesting all utility owners to field locate their <br /> facilities which may interfere with construction operations in both horizontal and vertical <br /> alignment. The utility owners are to be given reasonable notice by the Contractor before <br /> field location is needed. On request, the Engineer may make an inspection to verify that <br /> the utility company has field located its facilities, but will not assume responsibility for <br /> the accuracy of such work. The Contractor shall be responsible for maintaining the <br /> excavations or markers provided by the utility owners. This field location procedure may <br /> be waived if the utility owner has stated in writing to the Contractor and the Engineer it is <br /> satisfied the construction plans are sufficiently accurate. If the utility owner does not <br /> submit such statement, and they do not locate their facilities in both horizontal and <br /> vertical alignment, the Contractor shall, in writing, advise the Engineer. The Engineer <br /> may authorize the Contractor to proceed to locate the facilities in the most economical <br /> and reasonable manner. The Contractor will be paid according to Article 213 or Article <br /> 109.04 for such locations." <br /> 105.12 Inspection of Work. Hereby amended to include for this project as follows: <br /> "The Contractor shall give adequate advance notice of placing orders to permit tests to be <br /> completed before the materials are incorporated in the work and the Contractor shall <br /> afford such facilities as the Engineer may require for collecting and forwarding samples <br /> and making inspections. All costs associated with the furnishing and testing of samples <br /> will be borne by the Contractor. Independent testing laboratories may be used subject to <br /> the approval of the Engineer. <br /> 43 <br />