the rest of the bridge. In August 2006,the Illinois Department of Transportation(IDOT) directed the <br /> City to place a weight restriction on the bridge and to perform follow-up inspections every 6 months to <br /> monitor the outside beams of the bridge. Since the damaged beams are not in the wheel path, the bridge <br /> is safe for normal traffic; however, the 6 month inspections show that the bridge's deterioration is <br /> increasing. The bridge needs to be replaced before stricter traffic restrictions or full closure is required. <br /> Public input gathered as part of the design process indicated a desire to raise clearance height of the <br /> replacement bridge. The City Council supported the proposal to raise the bridge by 3 feet. <br /> $1,325,000 in Federal Surface Transportation Program—Urban (STU) funding is being requested to <br /> fund a portion of the bridge replacement cost. Current estimates show the bridge and roadway <br /> replacement cost at$2, 650,000 and the cost to raise and relocate the Sanitary District interceptor at <br /> $500,000. Federal funds are planned to pay 50%of the bridge replacement cost, with the balance being <br /> paid from the City's allotment of Motor Fuel Tax funds which are levied, collected and distributed by <br /> the State. <br /> Required Project Authorizations <br /> 1. The Local Agency Agreement with the State of Illinois authorizes the Illinois Department of <br /> Transportation to advertise for bids and award a contract to the lowest responsible bidder for the <br /> construction of the South Shores Bridge. The Agreement sets the funding to pay for the project <br /> based on the engineer's estimate of probable construction cost. The current division of cost is <br /> $1,325,000 in Federal funds and $1,825,000 in City funds including$500,000 to relocate the <br /> SDD interceptor. The interceptor costs will be reimbursed by the District. The$1,325,000 in <br /> Federal funds are pending approval by the Decatur Urban Transportation Study(DUATS) at a <br /> meeting scheduled for May 8. <br /> 2. This item appropriates $1,325,000 in Motor Fuel Tax(MFT) funds to pay the City's estimated <br /> portion of the South Shores Bridge project. The Sanitary District will reimburse the MFT fund <br /> for interceptor relocation costs currently estimated at $500,000. <br /> 3. This is the approval of an Intergovernmental Cooperation Agreement with the Sanitary District <br /> of Decatur to reimburse the City for project expenses related to the relocation of a District <br /> interceptor attached to the bridge. Under the agreement,the District will reimburse the City for <br /> the actual relocation cost which is currently estimated at $500,000. The Agreement is for <br /> $560,000 or actual costs and was passed by the District Board on March 2lt. <br /> 4. The amendment to the design services agreement between the City of Decatur and URS <br /> Corporation will retain the services of URS during the bridge construction and sewer relocation <br /> work. The City requires the services of URS to approve materials and detail drawings proposed <br /> by the contractor. In addition, questions or construction issues arise during the project that may <br /> require the assistance of URS to address. The construction engineering services for the South <br /> Shores Bridge project are for an additional fee of$30,000 which is added to the current <br /> authorized fee of$246,200, for a total not to exceed fee of$276,200. This fee is allocated in the <br /> MFT fund. <br /> Project Schedule <br /> Currently, the project is scheduled for a bid opening by IDOT on June 15, 2012. The South Shores <br /> Drive Bridge replacement work should begin in August with completion summer of 2013. One reason <br /> Page 12 <br />