R2011-181 APPROVING CONTRACT AMENDMENT
COD
>
City Clerk
>
RESOLUTIONS
>
2011
>
R2011-181 APPROVING CONTRACT AMENDMENT
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
8/31/2015 11:12:17 AM
Creation date
8/31/2015 11:12:11 AM
Metadata
Fields
Template:
Resolution/Ordinance
Res Ord Num
R2011-181
Res Ord Title
APPROVING CONTRACT AMENDMENT CHANGE ORDER NO.22 GLOBAL INFRASTRUCTURE, LLC LAKE DECATUR DAM REPAIRS
Department
Public Works
Approved Date
11/21/2011
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
7
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
Change Orders <br /> The work currently being conducted in the sluice gate area has exposed areas that are not visible <br /> during annual inspections or in the design process. Additional deterioration and damage has been <br /> discovered to the sluice gates as they have been removed from the structure for inspection. The <br /> gates are normally submerged making a thorough inspection impossible until they are removed. A <br /> change order has been prepared covering the proposed repairs that need to be made. <br /> Proposed Change Order 22 entails replacing the wearing surface along the ends of the sluice gates <br /> and on the guide slots the gates slide along. <br /> POTENTIAL OBJECTION: There are no known objections to this resolution. <br /> INPUT FROM OTHER SOURCES: Hanson Professional Services, and HDR Engineering <br /> STAFF REFERENCE: Keith Alexander, Director of Water Management, Richard Marley, Public <br /> Works Director, Matt Newell, City Engineer. Keith Alexander and Richard Marley will be in <br /> attendance at the City Council meeting to answer any questions of the Council on this item. <br /> BUDGEUTIME IMPLICATIONS: <br /> Budget Impact: Funding for this project is budgeted in the 2010 Project Fund. The additional cost <br /> for the requested change order is $50,000, for a total adjusted project cost of$3,442,023.34. <br /> Staffing Impact: Staffing is in place to oversee this work. <br /> This memorandum was prepared by Byron Bowman, Engineering Technician III, and reviewed by <br /> Matt Newell, City Engineer. <br /> Attach: 4 <br /> cc: Hanson Professional Services, Inc. <br /> Page 12 <br />