2. $173,649.83 for the final design ofthe streetscape improvements which includes an 80% <br /> ($138,919.86)reimbursement from the ITEP Grant and a City match of 20% <br /> ($34,729.97). <br /> The planned project schedule is as follows: <br /> • Attend FHWA Coordination Meeting (Completed) - May 7, 2008 <br /> • Approve Supplemental Agreement - May 19, 2008 <br /> • Conduct Public Information Meeting - June 2008 <br /> • Complete Project Development Report(Includes Preliminary Cost Estimate) -mid June 2008 <br /> • IDOT approval of Project Development Report - first week of July 2008 <br /> • Begin Final Design and Right of Way Negotiations - first week of July 2008 <br /> • Submit Preliminary Information and Concept Drawings to Council-August 2008 <br /> • Submit Pre-Final Design, Specifications and Estimate to IDOT -November 21, 2008 <br /> • Submit Final Design, Specifications and Estimate to IDOT - December 12, 2008 <br /> • Complete Right of Way Certification- January 21, 2009 <br /> • IDOT Contract Letting - March 9, 2009 <br /> City Council members will be invited to a public information meeting to be held in June. Information and <br /> concept drawings will be presented to Council in August. <br /> POTENTIAL OBJECTION: There are no known objections to this resolution. <br /> INPUT FROM OTHER SOURCES: Economic and Urban Development Department <br /> Illinois Department of Transportation <br /> URS Corporation <br /> STAFF REFERENCE: Greg Crowe, Director of Economic and Urban <br /> Development, at 424-2725 <br /> Rick Marley, Director of Engineering and <br /> Infrastructure, at 424-2747 <br /> Greg Crowe and Richard Marley will be in attendance at the City Council meeting to answer any <br /> questions of the Council on this item. <br /> BUDGET/TIME IMPLICATIONS: <br /> Funding for the final design services totals $292,327.60 of which$118,677.77 will be reimbursed by <br /> IDOT and$138,919.86 will be reimbursed by the ITEP Grant. The City's non-reimbursed expenditure <br /> for the added design work will be$34,729.97. This is in addition to the$154,705.74 originally approved <br /> in February, 2007, for a total of$447,033.34. The total City non-reimbursable expense is $65,671.16. <br /> Funds are allocated in the General Capital Fund for this work. <br /> Design work will begin immediately upon approval from the Illinois Department of Transportation which <br /> normally takes four to six weeks. Preliminary design sketches should be provided to the City Council in <br /> August. The intent is to have a project ready to begin during the 2009 construction season. <br /> Attach: 5 <br /> cc: Dick Borders, Municipal Services Manager <br /> Aaron Lawson, Assistant City Engineer <br /> URS Corporation <br /> Page � 2 <br />