- PROJECT COST AND AVAILABLE FUNDING -
<br /> MULTI-MODAL TRANSPORTATION FAC
<br /> ILITY
<br /> ANALYSIS
<br /> Bidders on this project were required to provide a"base bid" covering the construction of the
<br /> facility as specified on the published plans and drawings. Each bidder was also required to show
<br /> bids on five "alternates", which are possible minor changes such as replacing exterior wood trim
<br /> with aluminum-clad triin. (See attached sheet.) These alternates were supplied to the bidders in
<br /> the bidding package, and described as possible amendments to the plans. Seven general
<br /> contractors submitted bids by the deadline for bidding. The table below shows the seven bids in
<br /> the order that they were received and opened. Following the opening of the bids, it was
<br /> determined that alternates #1 and #2 were too costly and were discarded, while alternates#3, #4
<br /> and#5 were determined to be acceptable. The table below also shows the sum of the bids for
<br /> alternates #3, #4 and #5 for each bidder, and then each bidder's total bid.
<br /> BIDS RECEIVED
<br /> CONTRACTORS SUM OF
<br /> BASE BID � � TOTAL BID
<br /> (in the order received& o ened) ALT.s 3 + 4'+ 5�����'� �
<br /> Associated Constructors, LGC $1,385,000 $3,900 $1,388,900
<br /> Otto Baum Company, Inc. $1,555,000 ($8,720) $1,546,280
<br /> Mark A. Wolfer& Assoc. $1,712,000 $6,300 $1,718,300
<br /> Buildin S stemsofDecatur $1,555,000 $15,936 $1,570,936
<br /> Christ -Foltz, Inc. $1,515,420 $9,154 � $1,506,266
<br /> R.D. Lawrence Construction $1,702,9ll ($9,879) $1,693,032
<br /> BRH Builders $1,606,000 ($9,113) $1,596,887
<br /> The following table ranks the bidders by their base bid and then by their total bid. The order of
<br /> all seven bidders is the same under either ranking. In both cases, the low bidder is Associated
<br /> Constructors, LGC, and the next lowest bidder is Christy-Foltz, Inc. The difference between the
<br /> base bids of these two firms is $130,420; the difference between their total bids is $117,366.
<br /> RANKING BY BID
<br /> RANK BY BASE BID BY TOTAL BID
<br /> #1 Associated Constructors, LGC $1,385,000 Associated Constructars, LGC $1,388,900
<br /> #2 Christ -Foltz, Inc. $1,515,420 Christ -Foltz, Inc. $1,506,266
<br /> #3 Otto Baum Com an , Inc. $1,555,000 Otto Baum Com an , Inc. $1,546,280 �
<br /> #4 Buildin S stems of Decatur $1,555,000 Buildin S stems of Decatur $1,570,936
<br /> #5 BRH Builders $1,606,000 BRH Builders $1,596,887
<br /> #6 R.D. Lawrence Construction $1,702,911 R.D. Lawrence Construction $1,693,032
<br /> #7 Mark A. Wolfer& Assoc. $1,712,000 Mark A. Wolfer& Assoc. $1,718,300