' � given below. The net calendar day period shail be the total calendar period from <br /> start of a service to its completion less the calendar day periods from the date the <br /> documents were transmitted to the Owner for review and were returned to the <br /> Engineer and the calendar day periods from the dates the documents were <br /> transmitted to the IEPA for review and were returned to the Engineer. <br /> Service Calendar Days <br /> • Complete Design and Prepare <br /> Construction Contract Documents 180 days <br /> • Finalize Construction Documents <br /> Following IEPA and Owner Reviews 30 days <br /> • Bidding and Award Recommendation 60 days <br /> END OF ATTACHMENT B <br /> 09/30/99 B-3 <br /> CofDAttach6 <br /> slwl as <br />