Laserfiche WebLink
� ` Attachment#3 �I <br /> ` ` May 7, 1999 �, <br /> Page 1 of 1 <br /> AGREEMENT FOR ARCHITECTURAUENGINEERING SERVICES <br /> ATTACHMENT #3 - SCHEDULE <br /> The following is a schedule of major milestones to be the basis of this AGREEMENT: <br /> Weeks After Scheduled" <br /> Notice to Proceed Date <br /> PHASEI <br /> Demolition Documents Complete 4 Weeks June 14, 1999 <br /> Receive Demolition Bids 3 Weeks July 5, 1999 <br /> Award Demolition Contract 1 Week July 12, 1999 <br /> Begin Demolition 1 Week July 19, 1999 <br /> Complete Demolition 6 Weeks August 30, 1999 <br /> PHASE II <br /> Transportation Center Drawings Complete 13 Weeks August 16, 1999 <br /> Receive Transportation Center Bids 4 Weeks September 13, 1999 <br /> Award Transportation Center Contract 1 Week September 20, 1999 <br /> Begin Construction 1 Week September 27, 1999 <br /> Substantial Completion 38 Weeks June 19, 2000 <br /> ' Based upon May 17, 1999 Notice to Proceed. <br />