<br /> Project............................9924 -
<br /> .
<br /> ENGINEER'S EST'IMATE Dunn Company `
<br /> Bid Date...........................May 7, 1999 72a North Mercer
<br /> City Engineering Division Decatur,Illinois 62522
<br /> Time...............................2:00 p.m.
<br /> PAY ITEM UNIT QTY UNIT TOTAL UNIT TOTAL
<br /> PRICE PRICE
<br /> Incidental CA 6 TON 100 $23.00 $2,300.00 23.00 2,300.00 I
<br /> Base Construction, Cement Modified SY 72,500 $6.35 $460,375.00 6.45 467,625.00
<br /> Cement 100 WT 36,250 $5.40 $195,750.00 5.60 203,000.00
<br /> Excavation, Base Course SY 72,500 $4.20 $304,500.00 4.20 304,500.00
<br /> Bituminous Materials RC70/CSS-IH (Prime Coat) GAL 14,500 $1.50 $21,750.00 1.50 21,750.00
<br /> Bituminous Concrete Surface Course, Class I TON 12,180 $50.85 $619,353.00 50.75 618,135.00
<br /> PCC Driveway Removal&Replacement 6-in. SY 70 $39.50 $2,765.00 39.60 2,772.00
<br /> Valve Box Adjustment EA 115 $525.00 $60,375.00 530.00 60,950.00
<br /> Valve Box Frame and Lid EA 40 $75.00 $3,000.00 75.00 3,000.00
<br /> Manhole Adjustment EA 35 $735.00 $25,725.00 745.00 26,075.00
<br /> Manhole Concrete Flat Top 8-inch Thick EA 5 $200.00 $1,000.00 215.00 1,075.00
<br /> Manhole Frame& Lid Type 1,CL EA 35 $240.00 $8,400.00 245.00 8,575.00
<br /> Combination Concrete Curb&Gutter Removal& Replacement LF 500 $21.50 $10,750.00 22.00 11,000.00
<br /> Catch Basin TYIII, Fr. &Gr., 2' EA 1 $4,500.00 $4,500.00 2300.00 2,300.00
<br /> Truss Pipe#12 LF 30 $7.00 $210.00 28.60 858.00
<br /> TOTAL BID AS CORRECTED 1,720,753.00 1,733,915.00
<br /> Percent Over or Under ENGINEER'S ESTIMATE 0.76
<br /> The Apparent Low Bidder is: Dunn Company II
<br /> Stephen P. Swanson,City Engineer Date