, � CITY OF DECATUR, ILLINOIS �
<br /> ,. , MASS TRANSIT FACILITY
<br /> PROJECT NO. GC-8715
<br /> SCHEDULE OF PRICES
<br /> ' AS-BID PHASE I PHASE II
<br /> Bonds and Insurance . . . . . . . . . . . . . . . . . . . . . . . . $ 40,000 30,995 9,005
<br /> Overhead and Profit .. . . . . . . . . . . . .. . . . . . . . . 180,000 155,700 24, 300
<br /> Mobilization . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. 20, 000 20,000 0
<br /> Supervision . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 72,000 66,000 6,000
<br /> Project Sign . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 800 800 0
<br /> SITE WORK:
<br /> Demolition work . . . . . . . . . . . . . . . . . . . . . . . . . . . . 20,000 12,000 � 8,000
<br /> Landscape work . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 16,000 0 16,000
<br /> Earth work . . . . . . .. . . . . . .... .... .. .. ........ 20,000 20,000 U
<br /> Asphalt paving . . . . .. . . . .. . . . . . ... .. ... . .... �4,000 0 24,000
<br /> Concrete paving and curbs .. . . . .. . .. . ... .. . .. 220,000 0 220,000
<br /> Concrete walks . . . . . . . . . . . . . . . . . . . . .. .. . . . . . 13,000 0 13,000
<br /> Fencing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19,000 0 19,000
<br /> Utilities: Storm, sanitary, water, gas . . . . . 60,000 60,000 0
<br /> Fuel dispensing system . . . . . . . . . . . . . . . . . .. . . 20,000 0 20,000
<br /> Site Lighting and Underground Electric
<br /> Service . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . 30,000 9,000 21,000
<br /> Flag pole . . . . . . . . . . .. . . . . . . .. ... . .. .. . . . .. . 3,000 0 3,000
<br /> BUILDING WORK:
<br /> Subigrade work . . . . . . . . . . . . . . . . . . . . . .. . . . . . . 20,000 20,000 0
<br /> Sub+►drainage work . . . .. . . . . . . . . . . . . . . . . . . . . . 6,000 6,000 0
<br /> Concrete foundations and floors .. .. . . . . . . . . 95,000 95,000 0
<br /> Concrete pit, stairs, gratings . . . . .... . . . . . 25,000 25,000 - 0
<br /> Precast concrete .. . . . . . . . . . . . . . . . .. . .. . . . . . 10,000 10,000 0
<br /> Masonry . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 200,000 200,000 0
<br /> Pre-engineered steel frame . . . . . . . . .. . . . . . . . 95,000 95,000 0
<br /> Steel stairs . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . 5,000 0 5,000
<br /> Misc. metals . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . 25,000 21,215 3,785
<br /> Rough carpentry . . . . . . . . . . . . . . . . . . .. . . . . . . . . 7,000 7,000 0
<br /> Wood casework . . . . . . . . . . . . . . . . . . . . . .. . . . . .. . � 15,000 0 15,000
<br /> Roofing . . . . . . . . . . . . . . . . . . . . . . . .. ....... ... . 75,000 75,000 0
<br /> insulatfon . . . . . . . . . . .. . . . . . . . . .. . . .. . . . .. . . 15,000 15,000 0
<br /> Doors and Hardware . . . . .. . . . .. . . . . ..... .. . . . 24,000 24,000 0
<br /> Windows . . . . . . . . . . . . . ... . . . . . . . ... .. . . . . . . . . 27,000 27,000 0
<br /> Gypsum board & metal stud walls . ... . .. . . . . . 12,000 0 12,000
<br /> Carpet . . . . . . . . . . . . . . .. . . . . . . . . . . . . . . .. . .. . . 3,000 0 3,000
<br /> Epoxy flooring . . . . . . . . . . . . . . . . . . .. .. .. . . . . . 34,000 0 34,000
<br /> Ceramic tile . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 19,000 0 19,000
<br /> Vinyl tile . . . . . . . . . .. . . . . . . . . . . . ..... . . . . .. 4,000 0 4,000
<br /> Plaster . . . . . . . . . . . . . .. . . . . .. . . . . . .. . .. . . . . . 10,000 0 10,000
<br /> Acoustic ceilings . . . . . . . . . . .. . . . .. . . .. . . ... 10,000 0 10,000
<br /> Painting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . 24,000 0 24,000
<br /> Metal shelving . . . . . . . . . . . . . . . . . . . ... . . . . . . . 17,000 0 17,000
<br />
|