Route Various
<br /> E Illinois Department County Macon
<br /> of Transportation Local Agency City of Decatur
<br /> Section 16-00611 -00- RP
<br /> Engineer's Final Payment Estimate
<br /> Estimate No. 2 and Final Date of Completion 9/20/2016
<br /> Payable To: Name Otto Baum Company Inc.
<br /> Address 866 North Main, Morton, IL 61550
<br /> Items Awarded' Added Deducted Completed
<br /> Quantity Values Quantity Quantity Quantity Unit Price 7 Values
<br /> Totals from previous page
<br /> Earth Excavation 91.73 3,546.90 27.13 64.60 28.70 1,854.02
<br /> Lime 29.01 2,840.00 22.29 51.30 131.23 6,732.10
<br /> Processing Modified Soil,8 Inch 2,078.67 5,000.00 248.43 2.327.10 13.40 31,183.14
<br /> Aggregate-Temporary Access 44.29 2,506.68 44.29 44.49
<br /> Welded Wire Reinforcement 2,078.67 22,292.82 220.77 1.857.90 8.41 15,624.94
<br /> Portland Cement Conc.Pavement, 2,078.67 72.90 80.17 1,998.50 45.57 91,071.65
<br /> Portland Cement Conc. Driveway, 23.00 3,255.00 4.30 18.70 69.11 1,292.36
<br /> Portland Cement Conc.Sidewalk,5" 405.30 11,436.15 55.30 350.00 7.60 2,660.00
<br /> Detectable Warnings 20.00 5,000.00 10.40 30.40 30.38 923.55
<br /> Pavement Removal 2,078.67 83,988.02 78.97 1.999.70 9.49 18,977.15
<br /> Driveway Pavement Removal 87.00 35,238.65 9.20 77.80 15.90 1,237.02
<br /> Sidewalk Removal 270.20 648,148.48 6.40 263.80 10.25 2,703.95
<br /> Comb.Conc.Curb&Gutter 1,022.00 162.50 1,184.50 7.60 9,002.20
<br /> Catch Basins TBA With TY 3 F&G 6.00 6.00 1,898.75 11,392.50
<br /> Manholes TBA With New TY 1 4.00 4.00 1,790.25 7,161.00
<br /> Valve Box Frames TBA With New 2.00 2.00 1,410.50 2,821.00
<br /> CCC&G Type B-6.24 Dowelled 1,022.00 162.50 1,184.50 32.55 38,555.48
<br /> Paint Pavement Marking,6 Inch 130.00 167.00 297.00 3.26 968.22
<br /> Paint Pavement Marking,24 Inch 41.00 2.00 43:00 5.43 233.49
<br /> Aggregate Base Course,Special 67.25 34.15 33.10 27.94 924.81
<br /> High-Early PCC Driveway 40.00 20.80 19.20 58.59 1,124.93
<br /> Traffic Control and Protection 1.00 1.00 15,949.50 15,949.50
<br /> Modified Soil Mix Design&Field 1.00 1.00 3,282.13
<br /> Final Project Report 1.00 1.00 813.75
<br /> Hot Poured Joint Sealer 0.00 3,032.00 3,032.00 3.09 9,368.88
<br /> Permanent Survey Marker 0.00 170.09 170.09 1.00 170.09
<br /> Total Awarded Values $823,325.60 Total Completed Values $271,931.98
<br /> Page 1 of 2 BLR 13231 (Rev. 1/06)
<br /> Printed on 2/21/2017 2:34:58 PM