§ 5.1.2 The period covered by each Application for Payment shall be one calendar month ending on the last day of <br /> the month,or as follows: <br /> § 5.1.3 Provided that an Application for Payment is received by the Architect not later than the last day of a <br /> month,the Owner shall make payment of the certified amount to the Contractor not later than the last day of the <br /> following month.If an Application for Payment is received by the Architect after the application date fixed above, <br /> payment shall be made by the Owner not later than thirty ( 30 )days after the Architect receives the <br /> Application for Payment. <br /> (Federal, state or local laws may require payment within a certain period of time.) <br /> § 5.1.4 Each Application for Payment shall be based on the most recent schedule of values submitted by the <br /> Contractor in accordance with the Contract Documents.The schedule of values shall allocate the entire Contract <br /> Sum among the various portions of the Work.The schedule of values shall be prepared in such form and supported <br /> by such data to substantiate its accuracy as the Architect may require.This schedule,unless objected to by the <br /> Architect,shall be used as a basis for reviewing the Contractor's Applications for Payment. <br /> § 5.1.5 Applications for Payment shall show the percentage of completion of each portion of the Work as of the end <br /> of the period covered by the Application for Payment. <br /> § 5.1.6 Subject to other provisions of the Contract Documents,the amount of each progress payment shall be <br /> computed as follows: <br /> .1 Take that portion of the Contract Sum properly allocable to completed Work as determined by <br /> multiplying the percentage completion of each portion of the Work by the share of the Contract Sum <br /> allocated to that portion of the Work in the schedule of values,less retainage of ten percent( 10 <br /> %).Pending final determination of cost to the Owner of changes in the Work,amounts not in dispute <br /> shall be included as provided in Section 7.3.9 of AIA Document A201TM-2007,General Conditions <br /> of the Contract for Construction; <br /> .2 Add that portion of the Contract Sum properly allocable to materials and equipment delivered and <br /> suitably stored at the site for subsequent incorporation in the completed construction(or,if approved <br /> in advance by the Owner,suitably stored off the site at a location agreed upon in writing),less <br /> retainage of ten percent( 10 %); <br /> .3 Subtract the aggregate of previous payments made by the Owner;and <br /> .4 Subtract amounts,if any,for which the Architect has withheld or nullified a Certificate for Payment <br /> as provided in Section 9.5 of AIA Document A201-2007. <br /> § 5.1.7 The progress payment amount determined in accordance with Section 5.1.6 shall be further modified under <br /> the following circumstances: <br /> .1 Add,upon Substantial Completion of the Work,a sum sufficient to increase the total payments to the <br /> full amount of the Contract Sum,less such amounts as the Architect shall determine for incomplete <br /> Work,retainage applicable to such work and unsettled claims;and <br /> (Section 9.8.5 of AIA Document A201-2007 requires release of applicable retainage upon <br /> Substantial Completion of Work with consent of surety, if any.) <br /> .2 Add,if final completion of the Work is thereafter materially delayed through no fault of the <br /> Contractor,any additional amounts payable in accordance with Section 9.10.3 of AIA Document <br /> A201-2007. <br /> § 5.1.8 Reduction or limitation of retainage,if any,shall be as follows: <br /> (If it is intended,prior to Substantial Completion of the entire Work, to reduce or limit the retainage resulting from <br /> the percentages inserted in Sections 5.1.6.1 and 5.1.6.2 above, and this is not explained elsewhere in the Contract <br /> Documents, insert here provisions for such reduction or limitation.) <br /> None <br /> § 5.1.9 Except with the Owner's prior approval,the Contractor shall not make advance payments to suppliers for <br /> materials or equipment which have not been delivered and stored at the site. <br /> AIA Document A101 TM—2007.Copyright©1915,1918,1925,1937,1951,1958,1961,1963,1967,1974,1977,1987,1991,1997 and 2007 by The American <br /> Init. Institute of Architects.All rights reserved.WARNING:This AIA® Document is protected by U.S.Copyright Law and International Treaties.Unauthorized 6 <br /> reproduction or distribution of this AIA® Document,or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to <br /> the maximum extent possible under the law.This document was produced by AIA software at 14:52:24 on 11/18/2016 under Order No.4982744446_1 which <br /> expires on 07/01/2017,and is not for resale. <br /> User Notes: (1514818386) <br />