§ 3.2 REVIEW OF CONTRACT DOCUMENTS AND FIELD CONDITIONS BY CONTRACTOR
<br /> § 3.2.1 Execution of the Contract by the Contractor is a representation that the Contractor has visited the site,
<br /> become generally familiar with local conditions under which the Work is to be performed and correlated personal
<br /> observations with requirements of the Contract Documents.
<br /> § 3.2.2 Because the Contract Documents are complementary,the Contractor shall,before starting each portion of the
<br /> Work,carefully study and compare the various Contract Documents relative to that portion of the Work,as well as
<br /> the information furnished by the Owner pursuant to Section 2.2.3,shall take field measurements of any existing
<br /> conditions related to that portion of the Work,and shall observe any conditions at the site affecting it.These
<br /> obligations are for the purpose of facilitating coordination and construction by the Contractor and are not for the
<br /> purpose of discovering errors,omissions,or inconsistencies in the Contract Documents;however,the Contractor
<br /> shall promptly report to the Architect any errors,inconsistencies or omissions discovered by or made known to the
<br /> Contractor as a request for information in such form as the Architect may require.It is recognized that the
<br /> Contractor's review is made in the Contractor's capacity as a contractor and not as a licensed design professional,
<br /> unless otherwise specifically provided in the Contract Documents.
<br /> § 3.2.3 The Contractor is not required to ascertain that the Contract Documents are in accordance with applicable
<br /> laws,statutes,ordinances,codes,rules and regulations,or lawful orders of public authorities,but the Contractor
<br /> shall promptly report to the Architect any nonconformity discovered by or made known to the Contractor as a
<br /> request for information in such form as the Architect may require.
<br /> § 3.2.4 If the Contractor believes that additional cost or time is involved because of clarifications or instructions the
<br /> Architect issues in response to the Contractor's notices or requests for information pursuant to Sections 3.2.2 or
<br /> 3.2.3,the Contractor shall make Claims as provided in Article 15.If the Contractor fails to perform the obligations
<br /> of Sections 3.2.2 or 3.2.3,the Contractor shall pay such costs and damages to the Owner as would have been
<br /> avoided if the Contractor had performed such obligations.If the Contractor performs those obligations,the
<br /> Contractor shall not be liable to the Owner or Architect for damages resulting from errors,inconsistencies or
<br /> omissions in the Contract Documents,for differences between field measurements or conditions and the Contract
<br /> Documents,or for nonconformities of the Contract Documents to applicable laws,statutes,ordinances,codes,rules
<br /> and regulations,and lawful orders of public authorities.
<br /> § 3.3 SUPERVISION AND CONSTRUCTION PROCEDURES
<br /> 3.3.1 The Contractor§ o tractor shall supervise and direct the Work, using the Contractor's best skill and attention.The
<br /> Contractor shall be solely responsible for,and have control over,construction means,methods,techniques,
<br /> sequences and procedures and for coordinating all portions of the Work under the Contract,unless the Contract
<br /> Documents give other specific instructions concerning these matters.If the Contract Documents give specific
<br /> instructions concerning construction means,methods,techniques, sequences or procedures,the Contractor shall
<br /> evaluate the jobsite safety thereof and,except as stated below, shall be fully and solely responsible for the jobsite
<br /> safety of such means,methods,techniques,sequences or procedures.If the Contractor determines that such means,
<br /> methods,techniques,sequences or procedures may not be safe, the Contractor shall give timely written notice to the
<br /> Owner and Architect and shall not proceed with that portion of the Work without further written instructions from
<br /> the Architect.If the Contractor is then instructed to proceed with the required means,methods,techniques,
<br /> sequences or procedures without acceptance of changes proposed by the Contractor,the Owner shall be solely
<br /> responsible for any loss or damage arising solely from those Owner-required means,methods,techniques, sequences
<br /> or procedures.
<br /> § 3.3.2 The Contractor shall be responsible to the Owner for acts and omissions of the Contractor's employees,
<br /> Subcontractors and their agents and employees,and other persons or entities performing portions of the Work for,or
<br /> on behalf of,the Contractor or any of its Subcontractors.
<br /> § 3.3.3 The Contractor shall be responsible for inspection of portions of Work already performed to determine that
<br /> such portions are in proper condition to receive subsequent Work.
<br /> § 3.4 LABOR AND MATERIALS
<br /> § 3.4.1 Unless otherwise provided in the Contract Documents,the Contractor shall provide and pay for labor,
<br /> materials,equipment,tools,construction equipment and machinery,water,heat,utilities,transportation,and other
<br /> Init. AIA Document A201 TM—2007.Copyright©1911,1915,1918,1925,1937,1951,1958,1961,1963,1966,1970,1976,1987,1997 and 2007 by The American
<br /> Institute of Architects.All rights reserved.WARNING:This AIA® Document is protected by U.S.Copyright Law and International Treaties.Unauthorized 3
<br /> reproduction or distribution of this AIA® Document,or any portion of it,may result In severe civil and criminal penalties,and will be prosecuted to
<br /> / the maximum extent possible under the law.This document was produced by AIA software at 15:14:50 on 11/01/2016 under Order No.4982744446 1 which
<br /> expires on 07/01/2017,and is not for resale. —
<br /> User Notes: (2035499384)
<br />
|