§ 4.2.14 The Architect will review and respond to requests for information about the Contract Documents.The <br /> Architect's response to such requests will be made in writing within any time limits agreed upon or otherwise with <br /> reasonable promptness.If appropriate,the Architect will prepare and issue supplemental Drawings and <br /> Specifications in response to the requests for information. <br /> ARTICLE 5 SUBCONTRACTORS <br /> § 5.1 DEFINITIONS <br /> § 5.1.1 A Subcontractor is a person or entity who has a direct contract with the Contractor to perform a portion of <br /> the Work at the site.The term"Subcontractor"is referred to throughout the Contract Documents as if singular in <br /> number and means a Subcontractor or an authorized representative of the Subcontractor.The term "Subcontractor" <br /> does not include a separate contractor or subcontractors of a separate contractor. <br /> § 5.1.2 A Sub-subcontractor is a person or entity who has a direct or indirect contract with a Subcontractor to <br /> perform a portion of the Work at the site.The term"Sub-subcontractor"is referred to throughout the Contract <br /> Documents as if singular in number and means a Sub-subcontractor or an authorized representative of the <br /> Sub-subcontractor. <br /> § 5.2 AWARD OF SUBCONTRACTS AND OTHER CONTRACTS FOR PORTIONS OF THE WORK <br /> § 5.2.1 Unless otherwise stated in the Contract Documents or the bidding requirements,the Contractor,as soon as <br /> practicable after award of the Contract,shall furnish in writing to the Owner through the Architect the names of <br /> persons or entities(including those who are to furnish materials or equipment fabricated to a special design) <br /> proposed for each principal portion of the Work.The Architect may reply within 14 days to the Contractor in <br /> writing stating(1)whether the Owner or the Architect has reasonable objection to any such proposed person or <br /> entity or(2)that the Architect requires additional time for review.Failure of the Owner or Architect to reply within <br /> the 14-day period shall constitute notice of no reasonable objection. <br /> § 5.2.2 The Contractor shall not contract with a proposed person or entity to whom the Owner or Architect has made <br /> reasonable and timely objection.The Contractor shall not be required to contract with anyone to whom the <br /> Contractor has made reasonable objection. <br /> § 5.2.3 If the Owner or Architect has reasonable objection to a person or entity proposed by the Contractor,the <br /> Contractor shall propose another to whom the Owner or Architect has no reasonable objection.If the proposed but <br /> rejected Subcontractor was reasonably capable of performing the Work,the Contract Sum and Contract Time shall <br /> be increased or decreased by the difference,if any,occasioned by such change,and an appropriate Change Order <br /> shall be issued before commencement of the substitute Subcontractor's Work.However,no increase in the Contract <br /> Sum or Contract Time shall be allowed for such change unless the Contractor has acted promptly and responsively <br /> in submitting names as required. <br /> § 5.2.4 The Contractor shall not substitute a Subcontractor,person or entity previously selected if the Owner or <br /> Architect makes reasonable objection to such substitution. <br /> § 5.3 SUBCONTRACTUAL RELATIONS <br /> By appropriate agreement,written where legally required for validity,the Contractor shall require each <br /> Subcontractor,to the extent of the Work to be performed by the Subcontractor,to be bound to the Contractor by <br /> terms of the Contract Documents,and to assume toward the Contractor all the obligations and responsibilities, <br /> including the responsibility for safety of the Subcontractor's Work,which the Contractor,by these Documents, <br /> assumes toward the Owner and Architect.Each subcontract agreement shall preserve and protect the rights of the <br /> Owner and Architect under the Contract Documents with respect to the Work to be performed by the Subcontractor <br /> so that subcontracting thereof will not prejudice such rights,and shall allow to the Subcontractor,unless specifically <br /> provided otherwise in the subcontract agreement,the benefit of all rights,remedies and redress against the <br /> Contractor that the Contractor,by the Contract Documents,has against the Owner.Where appropriate,the <br /> Contractor shall require each Subcontractor to enter into similar agreements with Sub-subcontractors.The <br /> Contractor shall make available to each proposed Subcontractor,prior to the execution of the subcontract agreement, <br /> copies of the Contract Documents to which the Subcontractor will be bound,and,upon written request of the <br /> Subcontractor,identify to the Subcontractor terms and conditions of the proposed subcontract agreement that may <br /> AIA Document A20111—2007.Copyright©1911,1915,1918,1925,1937,1951,1958,1961,1963,1966,1970,1976,1987,1997 and 2007 by The American <br /> Init. Institute of Architects.All rights reserved.WARNING:This AIA® Document is protected by U.S.Copyright Law and International Treaties.Unauthorized 20 <br /> reproduction or distribution of this AIA® Document,or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to <br /> the maximum extent possible under the law.This document was produced by AIA software at 15:14:50 on 11/01/2016 under Order No.4982744446_1 which <br /> expires on 07/01/2017,and is not for resale. <br /> User Notes: (2035499384) <br />