Project Name: Parking Garages B&C Structural Improvements-Rebid Browning Chapman,LLC Western Waterproofing Golf Acquisition Group,LLC Tarlton Corporation
<br /> Engineer's Estimate 9900 Westpoint Drive Company,Inc. 141 E.141st St 5500 West Park Avenue
<br /> Project Number: 2015-03 Suite 128 DBA Western Specialty Hammond,IN 46327 St.Louis,MO 63110
<br /> Indianapolis,IN 46256 Contractors
<br /> Carl Walker 2501 N Colt Rd. Tom Chakos,Pres. Tracy E Hart,Pres.
<br /> Bid Date: Wednesday,March 8,2017 for Gordon L Chapman,VP Springfield,IL 62707 Will Markunas Nathan L Hart
<br /> City of Decatur J Allen Browning willmarkunascnr NLHart(catarltoncorp.com
<br /> Time: 10:00 A.M. abrowning a)browning Jeffrey J.Kelley,Pres golfconstruction.net
<br /> chapman.com Josh Woolard Ph. 314-633-3300
<br /> Fund: joshuaw(cowestern Ph. 312-498-0858 Fax 314-647-6038
<br /> Ph. 317-608-2775 specialtycontractors.com Fax None Listed
<br /> Organization Code: Fax 317-608-2763 Ph. 217-544-3474
<br /> Object Code: Fax 217-544-7615
<br /> Item Pay Item QTY Unit Unit Price Total Unit Price Total Unit Price Total Unit Price Total Unit Price Total
<br /> No.
<br /> 7.2A COVE JOINT SEALANT REPLACEMENT 50 LF $30.00 $1,500.00 $8.00 $400.00 $10.00 $500.00 $50.00 $2,500.00 $9.00 $450.00
<br /> 7.3A EXPANSION JOINT NOSING REPAIR 10 LF $185.00 $1,850.00 $100.00 $1,000.00 $95.00 $950.00 $250.00 $2,500.00 $150.00 $1,500.00
<br /> 7AA DECK COATING-LOCALIZED COATING REPAIRS 300 SF $13.25 $3,975.00 $9.00 $2,700.00 $15.00 $4,500.00 $17.50 $5,250.00 $25.00 $7,500.00
<br /> ALTERNATE BID C4-CLEAN AND PAINT STEEL BEAMS
<br /> 1.1 PROJECT MOBILIZATION 1 LS $2,010.00 $2,010.00 $7,000.00 $7,000.00 $2,160.00 $2,160.00 $1,000.00 $1,000.00 $1,750.00 $1,750.00
<br /> 1.2 PROJECT GENERAL REQUIREMENTS 1 LS $3,015.00 $3,015.00 $3,000.00 $3,000.00 $5,760.00 $5,760.00 $1,000.00 $1,000.00 $21,625.00 $21,625.00
<br /> 1.3 ALTERATIONS,CANCELLATIONS,EXTENSIONS,DEDUCTIONS& 1 ALLOW $3,500.00 $3,500.00 $3,500.00 $3,500.00 $3,500.00 $3,500.00 $3,500.00 $3,500.00 $3,500.00 $3,500.00
<br /> EXTRA WORK
<br /> 9.1A CLEAN AND PAINT STEEL BEAMS AND DECKING 7,500 SF $3.60 $27,000.00 $5.00 $37,500.00 $8.60 $64,500.00 $10.00 $75,000.00 $9.00 $67,500.00
<br /> 22.1A BROKEN/MISSING GRATE REPAIR 25 EA $260.00 $6,500.00 $300.00 $7,500.00 $160.00 $4,000.00 $500.00 $12,500.00 $155.00 $3,875.00
<br /> ALTERNATE BID C5-STRIPING
<br /> 1.1 PROJECT MOBILIZATION 1 LS $516.00 $516.00 $2,000.00 $2,000.00 $250.00 $250.00 $1,000.00 $1,000.00 $1,850.00 $1,850.00
<br /> 1.2 PROJECT GENERAL REQUIREMENTS 1 LS $774.00 $774.00 $1,000.00 $1,000.00 $650.00 $650.00 $1,000.00 $1,000.00 $7,000.00 $7,000.00
<br /> 1.3 ALTERATIONS,CANCELLATIONS,EXTENSIONS,DEDUCTIONS&
<br /> EXTRA WORK 1 ALLOW $900.00 $900.00 $900.00 $900.00 $900.00 $900.00 $900.00 $900.00 $900.00 $900.00
<br /> 32.1A PAVEMENT MARKINGS PAINTING 1 LS $8,600.00 $8,600.00 $11,500.00 $11,500.00 $7,000.00 $7,000.00 $8,000.00 $8,000.00 $15,250.00 $15,250.00
<br /> TOTAL BIDS GARAGE B AND C(AS CORRECTED) $577,517.90 $519,374.00 $610,627.00 F $677,380.00 F $877,125.00
<br /> Percent Over Under ENGINEER'S ESTIMATE 10.07% 5.73% F 1729% 5188%
<br /> TOTAL BASE BIDS GARAGE B AND C(AS CORRECTED) $275,902.15 $241,632.00 1 $275,852.001 $306,475.00 F $383,300.00
<br /> Percent Over Under ENGINEER'S ESTIMATE 12.42% 0.029% 11.08% 38.93%
<br /> BASE BIDS B&C+ALTERNATES B2&C4(AS CORRECTED) $363,619.15 $337,749.00 F $393,427.00 $452,075.00 $563,550.00
<br /> Percent Over Under ENGINEER'S ESTIMATE 7.11% 8.20% 24.339% 54.989%
<br /> Matthew C. Newell, P.E., City Engineer Date