Laserfiche WebLink
GENERAL CONDITIONS <br /> GC-28 TERMINATION FOR PUBLIC CONVENIENCE (continued) <br /> Acceptable materials, obtained by the Contractor for the work, that have been inspected, <br /> tested and accepted by the Engineer, and that are not incorporated in the work may, at the option <br /> of the Engineer, be purchased from the Contractor at actual costs as shown by receipted bills and <br /> actual cost records at such points of delivery as may be designated by the Engineer. <br /> Termination of a contract, as stated above will not relieve the Contractor or his/her surety <br /> of the responsibility of replacing defective work as required by the contract." <br /> END OF GENERAL CONDITIONS <br /> 43 <br />