My WebLink
|
Help
|
About
|
Sign Out
Home
Browse
Search
R2021-09 Resolution Authorizing a Professional Engineering Services Agreement with Clark Dietz Inc. to Provide Final Design Services for the Brush College and Reas Bridge Lift Station and Forcemain City Project 2020-06
COD
>
City Clerk
>
RESOLUTIONS
>
2021
>
R2021-09 Resolution Authorizing a Professional Engineering Services Agreement with Clark Dietz Inc. to Provide Final Design Services for the Brush College and Reas Bridge Lift Station and Forcemain City Project 2020-06
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
2/2/2021 3:59:15 PM
Creation date
2/2/2021 3:59:11 PM
Metadata
Fields
Template:
Resolution/Ordinance
Res Ord Num
R2021-09
Res Ord Title
R2021-09 Resolution Authorizing a Professional Engineering Services Agreement with Clark Dietz Inc. to Provide Final Design Services for the Brush College and Reas Bridge Lift Station and Forcemain City Project 2020-06
Department
Public Works
Approved Date
2/1/2021
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
38
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
BRUSH COLLEGE ROAD SEWER STUDY ( City of Decatur <br /> Table 3.Preliminary Opinion of Probable Project Costs <br /> Gravity Sewer $240,000 $1,650,500 $0 <br /> Pump Station $640,000 $75,000 $500,000 <br /> Forcemain $1,150,000 $0 $1,150,000 <br /> Land Acquisition/Easement $80,000 $0 $0 <br /> Addt'I Pump Station and FM $0 $0 $1,500,000 <br /> Damon Downstream Sewer Study $0 $150,000 $0 <br /> Contingency(30%) $633,000 $517,650 $945,000 <br /> Design Engineering(8%) $168,800 $138,040 $252,000 <br /> Construction Engineering(6%) $126,600 $103,530 $189,000 <br /> Total $3,038,400 $2,634,720 $4,536,000 <br /> Recommendations <br /> We recommend that for planning of this Service Area, improvements be divided into three phases as described <br /> herein.This phasing allows for reasonable capital expenditures and will avoid oversizing planned infrastructure <br /> before it is needed. Design of the first two phases should be such to anticipate Phase III flows for flexibility. <br /> Phase I recommendations include the following improvements: <br /> • The City purchase a 1-arce parcel for pump station at the Brush College Road and Reas Bridge <br /> Road intersection.Access to the pump station site should minimize traffic conflicts and be <br /> designed with enough space for operations and maintenance. <br /> • A new pump station with a wetwell sized for Phase II flows,valve vault,electrical controls,and <br /> generator.The pump station will also include two 30 hp pumps submersible pumps designed to <br /> SDD's design requirements for their operation and control. Physical space and electrical capacity <br /> should be available for Phase II flows, but the additional pump required for Phase II will not be <br /> installed. <br /> • An 8"forcemain will be installed along Hubbard Road to 27th Street. <br /> • Approximately 1,500 feet of gravity sewer will be install south along Brush College Road to provide <br /> service for the initial developments. <br /> Phase II recommendations include: <br /> • Prior to any improvement work,a sewer capacity study downstream of the Damon Avenue pump <br /> station is required to satisfy SDD's concerns about the remaining capacity in this sewer.This <br /> capacity study should: <br /> o Review the design capacity(slopes, pipe size,downstream constraints), <br /> o Televise to identify pipe condition, <br /> o Install flow monitoring at several locations along length of the sewer and collect several <br /> months of data, <br /> o Analyze the impact of rain events on sewer flow rates as compared to dry weather flow to <br /> determine how much of the capacity of the sewer is utilized during various design rainfall <br /> events, <br /> o Predict the likelihood and location of CSO/SSO events currently and with any additional flow <br /> from new developments in the service area,and <br /> o Recommend improvements and maximum remain capacity <br /> o Note:Any additional improvements recommended by the sewer capacity study downstream <br /> of the Damon Avenue pump station are not included here or in the cost estimates. <br /> • Add one additional 30-hp pump to the pump station. <br /> • Provide approximately 8,300 feet of additional gravity sewer to service new developments.These <br /> new gravity sewers should be installed as demand requires. <br /> Clark Dietz,Inc. 6 January 2021 <br />
The URL can be used to link to this page
Your browser does not support the video tag.