COMPENSABLE DELAY COSTS (BDE) <br /> Effective: June 2, 2017 <br /> Revised: April 1, 2019 <br /> Revise Article 107.40(b)of the Standard Specifications to read: <br /> "(b) Compensation. Compensation will not be allowed for delays, inconveniences, or <br /> damages sustained by the Contractor from conflicts with facilities not meeting the above <br /> definition; or if a conflict with a utility in an unanticipated location does not cause a <br /> shutdown of the work or a documentable reduction in the rate of progress exceeding the <br /> limits set herein. The provisions of Article 104.03 notwithstanding, compensation for <br /> delays caused by a utility in an unanticipated location will be paid according to the <br /> provisions of this Article governing minor and major delays or reduced rate of production <br /> which are defined as follows. <br /> ' (1) Minor Delay. A minor delay occurs when the work in conflict with the utility in an <br /> unanticipated location is completely stopped for more than two hours, but not to <br /> exceed two weeks. <br /> (2) Major Delay. A major delay occurs when the work in conflict with the utility in an <br /> unanticipated location is completely stopped for more than two weeks. <br /> (3) Reduced Rate of Production Delay. A reduced rate of production delay occurs when <br /> the rate of production on the work in conflict with the utility in an unanticipated <br /> location decreases by more than 25 percent and lasts longer than seven calendar <br /> days." <br /> Revise Article 107.40(c)of the Standard Specifications to read: <br /> "(c) Payment. Payment for Minor, Major, and Reduced Rate of Production Delays will be <br /> made as follows. <br /> ' (1) Minor Delay. Labor idled which cannot be used on other work will be paid for <br /> according to Article 109.04(b)(1) and (2) for the time between start of the delay and <br /> the minimum remaining hours in the work shift required by the prevailing practice in <br /> the area. <br /> Equipment idled which cannot be used on other work, and which is authorized to <br /> standby on the project site by the Engineer, will be paid for according to <br /> Article 109.04(b)(4). <br /> (2) Major Delay. Labor will be the same as for a minor delay. <br /> Equipment will be the same as for a minor delay, except Contractor-owned <br /> equipment will be limited to two weeks plus the cost of move-out to either the <br />