§11.2 Unless otherwise stated in the Contract Documents,the Contractor,as soon as practicable after award of the
<br /> Contract,shall notify the Owner and Architect of the Subcontractors or suppliers proposed for each of the principal
<br /> portions of the Work.The Contractor shall not contract with any Subcontractor or supplier to whom the Owner or
<br /> Architect has made reasonable written objection within ten days after receipt of the Contractor's list of
<br /> Subcontractors and suppliers.If the proposed but rejected Subcontractor was reasonably capable of performing the
<br /> Work,the Contract Sum and Contract Time shall be increased or decreased by the difference,if any,occasioned by
<br /> such change,and an appropriate Change Order shall be issued before commencement of the substitute
<br /> Subcontractor's Work.The Contractor shall not be required to contract with anyone to whom the Contractor has
<br /> made reasonable objection.
<br /> §11.3 Contracts between the Contractor and Subcontractors shall(1)require each Subcontractor,to the extent of the
<br /> Work to be performed by the Subcontractor,to be bound to the Contractor by the terms of the Contract Documents,
<br /> and to assume toward the Contractor all the obligations and responsibilities,including the responsibility for safety of
<br /> the Subcontractor's Work,which the Contractor,by the Contract Documents,assumes toward the Owner and
<br /> Architect,and(2)allow the Subcontractor the benefit of all rights,remedies and redress against the Contractor that
<br /> the Contractor,by these Contract Documents,has against the Owner.
<br /> ARTICLE 12 CONSTRUCTION BY OWNER OR BY SEPARATE CONTRACTORS
<br /> §12.1 The term"Separate Contractor(s)"shall mean other contractors retained by the Owner under separate
<br /> agreements.The Owner reserves the right to perform construction or operations related to the Project with the
<br /> Owner's own forces,and with Separate Contractors retained under Conditions of the Contract substantially similar
<br /> to those of this Contract,including those provisions of the Conditions of the Contract related to insurance and
<br /> waiver of subrogation.
<br /> §12.2 The Contractor shall afford the Owner and Separate Contractors reasonable opportunity for introduction and
<br /> storage of their materials and equipment and performance of their activities,and shall connect and coordinate the
<br /> Contractor's activities with theirs as required by the Contract Documents.
<br /> §12.3 The Owner shall be reimbursed by the Contractor for costs incurred by the Owner which are payable to a
<br /> Separate Contractor because of delays,improperly timed activities,or defective construction of the Contractor.The
<br /> Owner shall be responsible to the Contractor for costs incurred by the Contractor because of delays,improperly
<br /> timed activities,damage to the Work,or defective construction of a Separate Contractor.
<br /> ARTICLE 13 CHANGES IN THE WORK
<br /> §13.1 By appropriate Modification,changes in the Work may be accomplished after execution of the Contract.The
<br /> Owner,without invalidating the Contract,may order changes in the Work within the general scope of the Contract
<br /> consisting of additions,deletions,or other revisions,with the Contract Sum and Contract Time being adjusted
<br /> accordingly. Such changes in the Work shall be authorized by written Change Order signed by the Owner,
<br /> Contractor,and Architect,or by written Construction Change Directive signed by the Owner and Architect.Upon
<br /> issuance of the Change Order or Construction Change Directive,the Contractor shall proceed promptly with such
<br /> changes in the Work,unless otherwise provided in the Change Order or Construction Change Directive.
<br /> §13.2 Adjustments in the Contract Sum and Contract Time resulting from a change in the Work shall be determined
<br /> by mutual agreement of the parties or,in the case of a Construction Change Directive signed only by the Owner and
<br /> Architect,by the Contractor's cost of labor,material,equipment,and reasonable overhead and profit,unless the
<br /> parties agree on another method for determining the cost or credit.Pending final determination of the total cost of a
<br /> Construction Change Directive,the Contractor may request payment for Work completed pursuant to the
<br /> Construction Change Directive.The Architect will make an interim determination of the amount of payment due for
<br /> purposes of certifying the Contractor's monthly Application for Payment.When the Owner and Contractor agree on
<br /> adjustments to the Contract Sum and Contract Time arising from a Construction Change Directive,the Architect
<br /> will prepare a Change Order.
<br /> §13.3 The Architect will have authority to order minor changes in the Work not involving adjustment in the
<br /> Contract Sum or extension of the Contract Time and not inconsistent with the intent of the Contract Documents.
<br /> Such changes shall be effected by written order and shall be binding on the Owner and Contractor.The Contractor
<br /> shall carry out such written orders promptly.If the Contractor believes that the proposed minor change in the Work
<br /> Init. AIA Document A104—2017(formerly A107TM—2007).Copyright @ 1936,1951,1958,1961,1963,1966,1970,1974,1978,1987,1997,2007 and 2017.All
<br /> rights reserved.'The American Institute of Architects,""American Institute of Architects,""AIA,"the AIA Logo,and"AIA Contract Documents"are trademarks of 14
<br /> The American Institute of Architects.This document was produced at 14:33:21 CT on 01/31/2024 under Order No.3104238599 which expires on 05/21/2024,is
<br /> not for resale,is licensed for one-time use only,and may only be used in accordance with the AIA Contract Documents®Terms of Service.To report copyright
<br /> violations,e-mail docinfo@aiacontracts.com.
<br /> User Notes: (369ADA31D)
<br />
|