EXHIBIT A-1 <br /> CITY OF DECATUR - PUBLIC WORKS DEPARTMENT <br /> SANITARY SEWER SYSTEM REHABILITATION FOR <br /> LOST BRIDGE NORTH (TA_3N) & FLORIAN (TA_6) BASINS <br /> SCOPE OF DESIGN PHASE SERVICES <br /> GENERAL <br /> Crawford, Murphy & Tilly, Inc. (CMT) prepared the Sanitary Sewer Alternatives Analysis <br /> (SSAA) in 2017 for the Lost Bridge North (LBN) and Florian sewer basins that <br /> experienced basement backups and overflows due to extraneous water entering the <br /> sewer system from sewer main, manhole and sewer lateral defects, as well as illegal <br /> connections. The SSAA evaluated alternatives to eliminate SSOs and basement <br /> backups, prepared opinions of cost for each alternative and performed a cost-effective <br /> analysis to determine the preferred alternative. Each basin was evaluated and <br /> compared independently. <br /> The City of Decatur (COD) submitted the SSAA to USEPA-Region 5 in late 2017 and <br /> received approval of the plan on April 24, 2025. Contained in the approval letter was an <br /> implementation schedule for both basins that shows design starting in fiscal year (FY) <br /> 2027, construction starting in FY 2028 and completing construction by December 31, <br /> 2029 (FY 2029). Also noted in the approval letter is the desire of the COD to utilize the <br /> IEPA-Infrastructure Financial Assistance Section (IFAS) State Revolving Fund (SRF) to <br /> fund design and construction costs. <br /> A Project Plan (PP) was developed for the LBN and Florian Basins and submitted to <br /> IFAS on March 10, 2025 with the intent of the COD being listed on the IFAS Intended <br /> Funding List (IFL) that is expected to be published on or before June 30, 2027. A <br /> revised PP was submitted to IFAS on December 22, 2025. IFAS is expected to approve <br /> the PP in early 2026. <br /> The cost-effective alternatives described and identified in the PP from the SSAA are: <br /> 1. Alternative 2A for LBN, which includes sewer main and manhole rehabilitation, <br /> along with lower sewer lateral rehabilitation. This alternative provides a 5-year <br /> level of protection from rainfall derived inflow and infiltration (RDII). <br /> 2. Alternative 2A for Florian, which includes sewer main and manhole rehabilitation, <br /> along with lower sewer lateral rehabilitation. This alternative provides a 5-year <br /> level of protection from RDII. <br /> Obtaining SRF funds for this project is not guaranteed. To be successful with obtaining <br /> a loan from IFAS requires strategic planning to coordinate the design and construction <br /> schedules with the SRF loan application process so that construction work is completed <br /> by December 31, 2029. To meet the schedule requirements, the intent is to prepare one <br /> set of bidding documents that covers rehabilitation of sewer mains, manholes and <br /> sewer laterals. Generally, this goal is proposed to be accomplished in accordance with <br /> the following schedule. <br /> 24006892.01 A-1-1 02/19/2026 <br />