- -2- <br /> The original project schedule was April 1, 2012 to May 31, 2014. In order to fully complete the <br /> project, AWI is requesting a no cost time extension to August 31, 2014. City staff recommends <br /> that the City Council authorize the three month extension. <br /> POTENTIAL OBJECTION: <br /> None foreseen. <br /> STAFF REFERENCE: <br /> Keith Alexander, Director of Water Management, 217-424-2863 or kalexander@decaturil.gov <br /> BUDGET/TIME IMPLICATIONS: <br /> There are no budget implications. The extension will increase the length of the current <br /> agreement by three months. <br /> Attachments <br /> cc: Stephen John, AWI Executive Director <br />