.T ^ <br /> f <br /> Addendum No. 4 <br /> ' Lake Decatur Dredging and Oakley Sediment Basin Rehabilitation project <br /> Page 2 of 2 <br /> ' 3. Does the City intend for the Contractor to include the costs for extending Ameren <br /> overhead electric lines from the nearest existing pole to the Proposed Engineer's Field ! <br /> Ofce Location at Stare Rd(about 1,600 LF),or will the City provide this? i <br /> ' a.If the Contractor is to include extending Ameren overhead electric lines,will these <br /> lines need to be removed at the end of the contract? <br /> ' -Yes,please include the cost of providing power to the site from this location. We <br /> have discussed this arrangement with Ameren and they will supply a line of poles <br /> down the west side of Stare Road into the site.Please use$30,000 for bringing the <br /> power onto the site for bidding purposes. <br /> 4. The temporary easement shown on Sheet 38 for Addendum 3 how wide and how long? <br /> Are riprap trucks going to use this easement ? <br /> ' -The easement is approximately 550 feet long by 20 feet wide. Yes,the property owner <br /> has given permission for this access to be used by the Contractor. The property will <br /> ' need to be restored following construction of the basin. This cost shall be included in <br /> the unit price for the Stone Riprap Ditch. <br /> ' Sincerely, <br /> CHASTAIN&ASSOCIATES LLC <br /> ' Gregg L. Foltz,P.E. <br /> Project Manager <br /> i <br />