R2011-131 APPROVING CONTRACT AMENDMENT
COD
>
City Clerk
>
RESOLUTIONS
>
2011
>
R2011-131 APPROVING CONTRACT AMENDMENT
Metadata
Thumbnails
Annotations
Entry Properties
Last modified
8/31/2015 4:05:07 PM
Creation date
8/31/2015 4:05:06 PM
Metadata
Fields
Template:
Resolution/Ordinance
Res Ord Num
R2011-131
Res Ord Title
APPROVING CONTRACT AMENDMENT CHANGE ORDER NO. 15 GLOBAL INFRASTRUCTURE LAKE DECATUR DAM REPAIRS
Department
Public Works
Approved Date
8/15/2011
There are no annotations on this page.
Document management portal powered by Laserfiche WebLink 9 © 1998-2015
Laserfiche.
All rights reserved.
/
12
PDF
Print
Pages to print
Enter page numbers and/or page ranges separated by commas. For example, 1,3,5-12.
After downloading, print the document using a PDF reader (e.g. Adobe Reader).
View images
View plain text
Public Works Memorandum <br /> NO. 2011-57 <br /> DATE: August 8, 2011 <br /> TO: Honorable Mayor McElroy and City Council Members <br /> FROM: Ryan P. McCrady, City Manager <br /> Richard G. Marley, P.E., Director of Public Works <br /> Keith D. Alexander, Director of Water Management <br /> SUBJECT: Resolution Approving Contract Amendment Change Order No. 15, Global <br /> Infrastructure, Lake Decatur Dam Repairs, City Project 2009-02 <br /> SUMMARY RECOMMENDATION: <br /> It is recommended that the City Council approve the attached resolution authorizing additional <br /> funding, in the amount of$263,885.57,be added to the contract for the Lake Decatur Dam Repairs, <br /> City Project 2009-02, for a total project cost of$3,392,023.34. <br /> PRIOR COUNCIL ACTION: <br /> Appendix A provides a summary of prior Council actions. <br /> BACKGROUND: <br /> Summary of the Major Construction History of Lake Decatur Dam <br /> Appendix B provides a brief summary of past improvements to the Lake Decatur Dam. <br /> Lake Decatur Dam Repairs <br /> The Lake Decatur Dam Repairs project began in June, 2010. The project includes the following <br /> work: <br /> 1. Repairs to the upstream face of the dam. <br /> 2. Rehabilitation of the mechanical systems that raise and lower the sluice gates on the north <br /> side of the dam. <br /> 3. Replacing the seal systems for the bascule gates and sluice gates. <br /> 4. Removal of gate heaters along the bascule gates. <br /> 5. Installation of a concrete patch on the downstream spillway of the dam. <br /> 6. Replace all eight cylinders on the bascule gates of the dam. <br /> Currently, temporary bulkheads are installed on the lake side of the south bascule gate of the dam. <br /> These allow water to be drained from the bascule gate and provide opportunity for a thorough <br /> inspection of this portion of the dam. The bulkhead will remain in place while seals are replaced on <br /> the gates, some concrete repairs are made, and the hydraulic cylinders used to raise and lower the <br /> bascule gates are replaced. <br /> Page I 1 <br />