• -2- <br /> Attached are copies of the time extension requests from Christy-Foltz and a recommendation <br /> from Strand Associates to approve the extension. Approval will not negatively impact the <br /> proj ect. �' <br /> The original substantial completion date was August 28, 2009 and the original final completion <br /> date was October 2, 2009. The new substantial and final completion dates will be extended 60 <br /> calendar days to October 27, 2009 and December 1, 2009 respectively. <br /> POTENTIAL OBJECTION: <br /> None foreseen. <br /> INPUT FROM OTHER SOURCES: <br /> Christy-Foltz and Strand Associates. <br /> STAFF REFERENCE: <br /> Keith D. Alexander, Director of Water Management, 217-424-2863, kalexander@decaturil.gov <br /> BUDGET/TIME IMPLICATIONS: <br /> There are not budget implications. The contract substantial and final completion dates will be <br /> extended 60 calendar days. <br /> cc: Shane Zenz, Strand Associates <br /> Brian Blade, Christy-Foltz, Inc. <br />