<br /> .1 allowances shall cover the cost to the Contractor of materials and equipment delivered at the site and
<br /> all required taxes,less applicable trade discounts;
<br /> .2 Contractor's costs for unloading and handling at the site,labor, installation costs,overhead,profit and
<br /> other expenses contemplated for stated allowance amounts shall be included in the Contract Sum but
<br /> not in the allowances;
<br /> .3 whenever costs are more than or less than allowances, the Contract Sum shall be adjusted accordingly
<br /> by Change Order.The amount of the Change Order shall reflect(1)the difference between actual
<br /> costs and the allowances under Section 3.8.2.1 and(2)changes in Contractor's costs under Section
<br /> 3.8.2.2.
<br /> §3.8.3 Materials and equipment under an allowance shall be selected by the Owner in sufficient time to avoid delay
<br /> in the Work.
<br /> §3.9 SUPERINTENDENT ,
<br /> §3.9.1 The Contractor shall employ a competent superintendent and necessary assistants who shall be in attendance '
<br /> at the Project site during performance of the Work.The superintendent shall represent the Contractor,and ,
<br /> communications given to the superintendent shall be as binding as if given to the Contractor.Important
<br /> communications sha11 be confirmed in writing.Other communications shall be similarly confirmed on written
<br /> request in each case. '
<br /> §3.10 CONTRACTOR'S CONSTRUCTION SCHEDULES �,
<br /> §3.10.1 The Contractor,promptly after being awarded the Contract,shall prepare and submit for the Owner's and �,
<br /> Architect's information a Contractor's construction schedule for the Work.The schedule shall not exceed time limits �
<br /> current under the Contract Documents,shall be revised at appropriate intervals as required by the conditions of the II
<br /> Work and Project,shall be related to the entire Project to the extent required by the Contract Documents, and shall
<br /> provide for expeditious and practicable execution of the Work.
<br /> §3.10.2 The Contractor shall prepare and keep current,for the Architect's approval,a schedule of submittals which
<br /> is coordinated with the Contractor's construction schedule and allows the Architect reasonable time to review
<br /> submittals.
<br /> §3.10.3 The Contractor shall perform the Work in general accordance with the most recent schedules submitted to
<br /> the Owner and Architect.
<br /> §3.11 DOCUMENTS AND SAMPLES AT THE SITE
<br /> §3.11.1 The Contractor shall maintain at the site for the Owner one record copy of the Drawings,Specifications,
<br /> Addenda,Change Orders and other Modifications,in good order and marked currently to record field changes and
<br /> selections made during construction, and one record copy of approved Shop Drawings,Product Data, Samples and
<br /> similar required submittals.These shall be available to the Architect and shall be delivered to the Architect for
<br /> submittal to the Owner upon completion of the Work.
<br /> §3.12 SHOP DRAWINGS,PRODUCT DATA AND SAMPLES
<br /> §3.12.1 Shop Drawings are drawings,diagrams, schedules and other data specially prepared for the Work by the
<br /> Contractor or a Subcontractor,Sub-subcontractor,manufacturer, supplier or distributor to illustrate some portion of
<br /> the Work.
<br /> §3.12.2 Product Data are illustrations,standard schedules,performance charts,instructions,brochures,diagrams and
<br /> other information furnished by the Contractor to illustrate materials or equipment for some portion of the Work.
<br /> §3.12.3 Samples are physical examples which illustrate materials,equipment or workmanship and establish
<br /> standards by which the Work will be judged.
<br /> §3.12.4 Shop Drawings,Product Data, Samples and similar submittals are not Contract Documents.The purpose of
<br /> their submittal is to demonstrate for those portions of the Work for which submittals are required by the Contract
<br /> Documents the way by which the Contractor proposes to conform to the information given and the design concept
<br /> expressed in the Contract Documents.Review by the Architect is subject to the limitations of Section 4.2J.
<br /> Informational submittals upon which the Architect is not expected to take responsive action may be so identified in
<br /> AIA Document A201 TM—1997.Copyright �O 1911,1915,1918,1925,1937,1951,1958,1961,1963,1966,1970,1976,1987 and 1997 by The American
<br /> Institute of Architects. All rights reserved. WARNING:This AIA� Document is protected by U.S.Copyright Law and International Treaties. 15
<br /> Unauthorized reproduction or distribution of ihis AIA�'Document,or any portion of it,may result in severe civil and criminal penalties,and will be
<br /> prosecuted to the maximum extent possible under the law. This document was produced by AIA software at 16:16:56 on 03/13/2007 under Order
<br /> No.UNLICENSED which expires on 11/18/2007,and is not for resale.
<br /> User Notes: (2584627897)