Annual Sanitary Sewer Cleaning Engineer's Estimate Hoerr Construction, Inc. Bodine Services, Inc.
<br /> City Project 2003-11 PO Box 10195 5330 E. Firehouse Road .
<br /> ity Engineering Divisio Peoria, IL 61612 Decatur, IL 62521
<br /> Bid Date.. Monday, June 30, 2003 I,
<br /> Time.. 10:00 a.m. 'I
<br /> Sanitary Sewer Fund I
<br /> ACCOUNT NO.. 79-40000-668 I
<br /> .............................................................
<br /> ENG. CODE....................................................................SS2003-11
<br /> ITEM PAY ITEM QUANTITY UNIT UNIT PRICE TOTAL UNIT PRICE TOTAL UNIT PRICE TOTAL
<br /> NUMBER
<br /> SS0010 Sewer Line Cleaning, 8 Inch 35,000 LF $1.85 $64,750.00 $0.76 $26,600.00 $1.75 $61,250.00
<br />� SS0011 Sewer Line Cleaning, 10 Inch 30,000 LF $1.90 $57,000.00 $0.80 $24,000.00 $1.75 $52,500.00
<br /> SS0011 Sewer Line Cleaning, 12 Inch 20,000 LF $1.95 $39,000.00 $0.84 $16,800.00 $1.75 $35,000.00
<br /> SS0011 Sewer Line Cleaning, 15 Inch 5,500 LF $2.05 $11,275.00 $0.90 $4,950.00 $1.70 $9,350.00
<br /> SS0011 Sewer Line Cleaning, 18 Inch 6,500 LF $2.15 $13,975.00 $1.50 $9,750.00 $1.70 $11,050.00
<br /> SS00121 Sewer Line Cleaning, 21 Inch 1,500 LF $2.25 $3,375.00 $1.60 $2,400.00 $1.65 $2,475.00
<br /> SS0012 Sewer Line Cleaning, 24 Inch 2,500 LF $2.35 $5,875.00 $1.70 $4,250.00 $1.65 $4,125.00
<br /> TOTAL BID As Corrected $195,250.00 $88,750.00 $175,750.00
<br /> Percent Over or Under ENGINEER'S ESTIMATE -54.55% -9.99%
<br /> ��/-v3
<br /> Ma hew C. Newell, P.E., City Engineer Date