� � + � <br /> Page 2 <br /> As noted on the table, the bid prices received are well under the Engineer's Estimate. Estimates <br /> are generally based upon past work of a similar nature that has been completed. As in the table <br />' above, the variations are often significant between bidders. City staff will normally estimate a <br />' median cost for the various items in a contract. As expected, median costs should be higher than <br /> a low bid. This estimation practice when used on comparable projects in combination with a <br /> competitive bidding environment will often produce bids lower than the estimate. <br /> The structure of this contract is such that additional manhole or sewer line replacement work can <br /> be added as needs are identified that cannot wait on or are impractical for a new contract to be <br /> prepared, advertised and awarded. In all likelihood, additional manhole and sewer problems <br /> requiring immediate attention will be identified prior to the end of the fiscal year. Staff desires to <br /> take advantage of the excellent bid received and requests the authority to expend up to an <br /> additional $25,000 under this project to address other manhole / sewer problems as they arise. If <br /> necessity dictates that the additional funds be fully expended, the final outlay will be less than the <br /> original Engineer's Estimate for the project. <br /> POTENTIAL OBJECTION: There are no known objections to this resolution <br /> and bid award. <br /> INPUT FROM OTHER SOURCES: None <br /> STAFF REFERENCE: Matt Newell, City Engineer, at 424-2747 <br /> The City Engineer, Matt Newell, will be in attendance at the City Council meeting to answer any <br /> questions of the Council on this item. <br /> BUDGET/TIME IMPLICATIONS: <br /> Funding for this project is currently budgeted in the City's Sanitary Sewers Fund. The <br /> recommended low bid amount is $48,915.00. The resolution also authorizes an additional <br /> $25,000 which may increase the project up to $73,915.00. <br /> The project is scheduled to begin October 2001 and should be completed within 2 months. The <br /> project will be held open until the end of the fiscal year to address additional sanitary sewer <br /> problems as they are identified. <br /> attach: 2 <br /> cc: John Smith, Assistant City Manager of Public Services <br /> Dave Schmidt,Bodine Services, Inc. <br /> Chris Entler, Entler Excavating Co., Inc. <br />