, <br /> :' <br /> EXHIBIT A—SCOPE OF WORK <br /> CITY OF DECATUR <br /> CLARIFIER CONVERSION PROJECT <br /> PRIMARY BASIN NO. 2 & SECONDARY BASIN NO. 2 <br /> (EAST TREATMENT TRAIN) <br /> SCOPE OF PROJECT <br /> The Project Scope for the city of Decatur Clarifier Conversion Project, Phase I — East <br /> Treatment Train shall consist of the following areas of work. <br /> A. Convert the east treatment train primary and secondary clarifiers to 71'-6" diameter, single <br /> stage helical upflow lime softening clarifiers within the same footprint as the existing <br /> clarifiers. Modify piping as required for new clarifiers. <br /> B. Add anionic polymer chemical storage and feed system/piping for the east treatment train <br /> clarifiers. <br /> C. Modify the existing lime feed system to allow pumping of lime individually to both of the <br /> converted east treatment train clarifiers. <br /> D. Allow for sequencing such that the west treatment train primary and secondary clarifiers <br /> remain online and operational during the east treatment train conversion. Provide flow <br /> splitting/diversion structures and piping that will be required to accomplish this sequencing <br /> and allow long-term operational resilience. <br /> E. Evaluate the existing clarifier sludge pumps. It is assumed that the pumps may need to be <br /> replaced. These same pumps will also be used for dewatering of the clarifiers. <br /> DESIGN PHASE SERVICES <br /> The Scope of Services for the City of Decatur Clarifier Conversion Project, East Treatment <br /> Train design services shall consist of the following tasks: <br /> 1. Review existing background information. Review existing plans and reports relevant <br /> to the project design. <br /> 2. Site Visits. Conduct site visits to verify existing conditions and obtain information <br /> required for design. <br /> 3. Project Kickoff Meeting. Conduct a project kickoff ineeting at the Decatur water <br /> treatment plant with client and CMT staff. In addition to the Project Manager other staff <br /> at the meeting will include process mechanical, mechanical, structural and electrical staff <br /> as necessary. <br /> 4. Field Surveying <br /> a. Utilize horizontal and vertical control based on information from the 1985 B & V <br /> project. <br /> b. Complete topographic survey of the project site as required for project. <br /> c. Point processing and generate AutoCAD C3D drawing for the survey limits <br /> d. QA/QC - field visit to spot check survey data. <br /> e. Conduct 3D laser surveying in piping tunnels. <br /> A1 <br />