Mr. William B. Sands October 10, 1991 Page 2 <br /> Co. , of East Peroria, in the amount of $79,880. The bid <br /> from Capitol was $6 ,016, or 8. 1 percent greater than the low <br /> bid. <br /> The low bidder for the Division III work was Harshman <br /> Plumbing, Heating and Electrical Co. , of Sullivan. That bid <br /> was in the amount of $45,446. The second low, and only <br /> other, bid was from Entler Excavating Co. , of Decatur. That <br /> bid was in the amount of $46,446. <br /> We have revised the Engineers Estimate for the work of <br /> Divisions I and II , to consider the 10—inch pump and the <br /> reduced pumping head and horsepower requirement , and those <br /> dollar amounts are shown for comparison with the low bid <br /> figures. <br /> Enginers Estimate Harshman <br /> Division I, pumps and drives $162, 202 $129 , 949 <br /> Division II , diesel engines 87,300 73,864 <br /> Division III, installation 33,400 45, 466 <br /> Totals $282 ,902 $249 , 279 <br /> We recommend that the award be made to Harshman <br /> Plumbing , Heating , and Electrical Co. , in the amout of <br /> � $249, 279. <br /> We are very pleased with the amount, and spread , of the <br /> bids. It is noted that the construction cost per well , <br /> including the well , pumps, angle drives and engines, totals <br /> only a little over $125 ,000. The total number of we11s has <br /> been reduced from ten to eight , and it appears that the <br /> total costs per well will be considerably below the budgeted <br /> amount of $150,000. <br /> The bid documents are returned to your office herewith. <br /> Since e y <br /> . �...,� <br /> Joh C. uillou <br />