Laserfiche WebLink
Burdick will have substantially completed the project by the original contract completion date of <br /> November 18, 2016 and will complete project wrap up tasks such as final soil grading, lawn <br /> shaping, seeding, asphalt and concrete work in the spring of 2017. No additional expenses will <br /> be necessary for this work. <br /> SCHEDULE <br /> It is planned to have the wrap up work begin in March and the project be completed by May 17, <br /> 2017. <br /> POTENTIAL OBJECTION <br /> There are no known objections. <br /> INPUT FROM OTHER SOURCES <br /> Burdick Plumbing and Heating Company, Inc. <br /> STAFF REFERENCE <br /> Keith Alexander, Director of Water Management (add contact info) <br /> Jerry Stevens, Engineering Services Coordinator (add contact info) <br /> BUDGET/TIME IMPLICATIONS <br /> There will not be any changes to the contract cost. The project will be completed by May 17, <br /> 2017. <br /> Cc: Jared Burdick, Burdick Plumbing & Heating Company, Inc. <br />