§ 3.18 INDEMNIFICATION
<br /> § 3.18.1 To the fullest extent permitted by law the Contractor shall indemnify and hold harmless the Owner,
<br /> Architect,Architect's consultants,and agents and employees of any of them from and against claims, damages,
<br /> losses and expenses,including but not limited to attorneys' fees,arising out of or resulting from performance of the
<br /> Work,provided that such claim,damage,loss or expense is attributable to bodily injury,sickness,disease or death,
<br /> or to injury to or destruction of tangible property(other than the Work itself),but only to the extent caused by the
<br /> negligent acts or omissions of the Contractor,a Subcontractor,anyone directly or indirectly employed by them or
<br /> anyone for whose acts they may be liable,regardless of whether or not such claim,damage,loss or expense is
<br /> caused in part by a party indemnified hereunder.Such obligation shall not be construed to negate,abridge,or reduce
<br /> other rights or obligations of indemnity that would otherwise exist as to a party or person described in this Section
<br /> 3.18.
<br /> § 3.18.2 In claims against any person or entity indemnified under this Section 3.18 by an employee of the
<br /> Contractor,a Subcontractor,anyone directly or indirectly employed by them or anyone for whose acts they may be
<br /> liable,the indemnification obligation under Section 3.18.1 shall not be limited by a limitation on amount or type of
<br /> damages, compensation or benefits payable by or for the Contractor or a Subcontractor under workers'
<br /> compensation acts,disability benefit acts or other employee benefit acts.
<br /> ARTICLE 4 ARCHITECT
<br /> § 4.1 GENERAL
<br /> § 4.1.1 The Owner shall retain an architect lawfully licensed to practice architecture or an entity lawfully practicing
<br /> architecture in the jurisdiction where the Project is located.That person or entity is identified as the Architect in the
<br /> Agreement and is referred to throughout the Contract Documents as if singular in number.
<br /> § 4.1.2 Duties,responsibilities and limitations of authority of the Architect as set forth in the Contract Documents
<br /> shall not be restricted,modified or extended without written consent of the Owner,Contractor and Architect.
<br /> Consent shall not be unreasonably withheld.
<br /> § 4.1.3 If the employment of the Architect is terminated,the Owner shall employ a successor architect as to whom
<br /> the Contractor has no reasonable objection and whose status under the Contract Documents shall be that of the
<br /> Architect.
<br /> § 4.2 ADMINISTRATION OF THE CONTRACT
<br /> § 4.2.1 The Architect will provide administration of the Contract as described in the Contract Documents and will be
<br /> an Owner's representative during construction until the date the Architect issues the final Certificate for Payment.
<br /> The Architect will have authority to act on behalf of the Owner only to the extent provided in the Contract
<br /> Documents.
<br /> § 4.2.2 The Architect will visit the site at intervals appropriate to the stage of construction,or as otherwise agreed
<br /> with the Owner,to become generally familiar with the progress and quality of the portion of the Work completed,
<br /> and to determine in general if the Work observed is being performed in a manner indicating that the Work,when
<br /> fully completed,will be in accordance with the Contract Documents.However,the Architect will not be required to
<br /> make exhaustive or continuous on-site inspections to check the quality or quantity of the Work.The Architect will
<br /> not have control over,charge of,or responsibility for,the construction means,methods,techniques,sequences or
<br /> procedures,or for the safety precautions and programs in connection with the Work,since these are solely the
<br /> Contractor's rights and responsibilities under the Contract Documents,except as provided in Section 3.3.1.
<br /> § 4.2.3 On the basis of the site visits,the Architect will keep the Owner reasonably informed about the progress and
<br /> quality of the portion of the Work completed,and report to the Owner(1)known deviations from the Contract
<br /> Documents and from the most recent construction schedule submitted by the Contractor,and(2)defects and
<br /> deficiencies observed in the Work.The Architect will not be responsible for the Contractor's failure to perform the
<br /> Work in accordance with the requirements of the Contract Documents.The Architect will not have control over or
<br /> charge of and will not be responsible for acts or omissions of the Contractor,Subcontractors,or their agents or
<br /> employees,or any other persons or entities performing portions of the Work.
<br /> AIA Document A20111—2007.Copyright©1911,1915,1918,1925,1937,1951,1958,1961,1963,1966,1970,1976,1987,1997 and 2007 by The American
<br /> Init. Institute of Architects.All rights reserved.WARNING:This AIA® Document is protected by U.S.Copyright Law and International Treaties.Unauthorized 18
<br /> reproduction or distribution of this AIA® Document,or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to
<br /> the maximum extent possible under the law.This document was produced by AIA software at 15:14:50 on 11/01/2016 under Order No.4982744446_1 which
<br /> expires on 07/01/2017,and is not for resale.
<br /> User Notes: (2035499384)
<br />
|