required to provide professional services in violation of applicable law.If professional design services or
<br /> certifications by a design professional related to systems,materials or equipment are specifically required of the
<br /> Contractor by the Contract Documents,the Owner and the Architect will specify all performance and design criteria
<br /> that such services must satisfy.The Contractor shall cause such services or certifications to be provided by a
<br /> properly licensed design professional,whose signature and seal shall appear on all drawings,calculations,
<br /> specifications,certifications,Shop Drawings and other submittals prepared by such professional. Shop Drawings
<br /> and other submittals related to the Work designed or certified by such professional,if prepared by others,shall bear
<br /> such professional's written approval when submitted to the Architect.The Owner and the Architect shall be entitled
<br /> to rely upon the adequacy, accuracy and completeness of the services,certifications and approvals performed or
<br /> provided by such design professionals,provided the Owner and Architect have specified to the Contractor all
<br /> performance and design criteria that such services must satisfy. Pursuant to this Section 3.12.10,the Architect will
<br /> review,approve or take other appropriate action on submittals only for the limited purpose of checking for
<br /> conformance with information given and the design concept expressed in the Contract Documents.The Contractor
<br /> shall not be responsible for the adequacy of the performance and design criteria specified in the Contract
<br /> Documents.
<br /> § 3.13 USE OF SITE
<br /> The Contractor shall confine operations at the site to areas permitted by applicable laws, statutes,ordinances,codes,
<br /> rules and regulations,and lawful orders of public authorities and the Contract Documents and shall not unreasonably
<br /> encumber the site with materials or equipment.
<br /> § 3.14 CUTTING AND PATCHING
<br /> § 3.14.1 The Contractor shall be responsible for cutting,fitting or patching required to complete the Work or to
<br /> make its parts fit together properly.All areas requiring cutting,fitting and patching shall be restored to the condition
<br /> existing prior to the cutting,fitting and patching,unless otherwise required by the Contract Documents.
<br /> § 3.14.2 The Contractor shall not damage or endanger a portion of the Work or fully or partially completed
<br /> construction of the Owner or separate contractors by cutting,patching or otherwise altering such construction,or by
<br /> excavation.The Contractor shall not cut or otherwise alter such construction by the Owner or a separate contractor
<br /> except with written consent of the Owner and of such separate contractor;such consent shall not be unreasonably
<br /> withheld.The Contractor shall not unreasonably withhold from the Owner or a separate contractor the Contractor's
<br /> consent to cutting or otherwise altering the Work.
<br /> § 3.15 CLEANING UP
<br /> § 3.15.1 The Contractor shall keep the premises and surrounding area free from accumulation of waste materials or
<br /> rubbish caused by operations under the Contract.At completion of the Work,the Contractor shall remove waste
<br /> materials,rubbish,the Contractor's tools,construction equipment,machinery and surplus materials from and about
<br /> the Project.
<br /> § 3.15.2 If the Contractor fails to clean up as provided in the Contract Documents,the Owner may do so and Owner
<br /> shall be entitled to reimbursement from the Contractor.
<br /> § 3.16 ACCESS TO WORK
<br /> The Contractor shall provide the Owner and Architect access to the Work in preparation and progress wherever
<br /> located.
<br /> § 3.17 ROYALTIES, PATENTS AND COPYRIGHTS
<br /> The Contractor shall pay all royalties and license fees.The Contractor shall defend suits or claims for infringement
<br /> of copyrights and patent rights and shall hold the Owner and Architect harmless from loss on account thereof,but
<br /> shall not be responsible for such defense or loss when a particular design,process or product of a particular
<br /> manufacturer or manufacturers is required by the Contract Documents,or where the copyright violations are
<br /> contained in Drawings,Specifications or other documents prepared by the Owner or Architect.However,if the
<br /> Contractor has reason to believe that the required design,process or product is an infringement of a copyright or a
<br /> patent,the Contractor shall be responsible for such loss unless such information is promptly furnished to the
<br /> Architect.
<br /> Init. AIA Document A20111—2007.Copyright 01911,1915,1918,1925,1937,1951,1958,1961,1963,1966,1970,1976,1987,1997 and 2007 by The American
<br /> Institute of Architects.All rights reserved.WARNING:This AIAm Document is protected by U.S.Copyright Law and International Treaties.Unauthorized 17
<br /> reproduction or distribution of this AIA® Document,or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to
<br /> / the maximum extent possible under the law.This document was produced by AIA software at 15:14:50 on 11/01/2016 under Order No.4982744446 1 which
<br /> expires on 07/01/2017,and is not for resale. —
<br /> User Notes: (2035499384)