the Owner's or separate contractor's completed or partially completed construction is fit and proper to receive the <br /> Contractor's Work,except as to defects not then reasonably discoverable. <br /> § 6.2.3 The Contractor shall reimburse the Owner for costs the Owner incurs that are payable to a separate <br /> contractor because of the Contractor's delays,improperly timed activities or defective construction.The Owner shall <br /> be responsible to the Contractor for costs the Contractor incurs because of a separate contractor's delays,improperly <br /> timed activities,damage to the Work or defective construction. <br /> § 6.2.4 The Contractor shall promptly remedy damage the Contractor wrongfully causes to completed or partially <br /> completed construction or to property of the Owner or separate contractors as provided in Section 10.2.5. <br /> § 6.2.5 The Owner and each separate contractor shall have the same responsibilities for cutting and patching as are <br /> described for the Contractor in Section 3.14. <br /> § 6.3 OWNER'S RIGHT TO CLEAN UP <br /> If a dispute arises among the Contractor,separate contractors and the Owner as to the responsibility under their <br /> respective contracts for maintaining the premises and surrounding area free from waste materials and rubbish,the <br /> Owner may clean up and the Architect will allocate the cost among those responsible. <br /> ARTICLE 7 CHANGES IN THE WORK <br /> § 7.1 GENERAL <br /> § 7.1.1 Changes in the Work may be accomplished after execution of the Contract,and without invalidating the <br /> Contract,by Change Order,Construction Change Directive or order for a minor change in the Work,subject to the <br /> limitations stated in this Article 7 and elsewhere in the Contract Documents. <br /> § 7.1.2 A Change Order shall be based upon agreement among the Owner,Contractor and Architect;a Construction <br /> Change Directive requires agreement by the Owner and Architect and may or may not be agreed to by the <br /> Contractor;an order for a minor change in the Work may be issued by the Architect alone. <br /> § 7.1.3 Changes in the Work shall be performed under applicable provisions of the Contract Documents,and the <br /> Contractor shall proceed promptly,unless otherwise provided in the Change Order,Construction Change Directive <br /> or order for a minor change in the Work. <br /> § 7.2 CHANGE ORDERS <br /> § 7.2.1 A Change Order is a written instrument prepared by the Architect and signed by the Owner,Contractor and <br /> Architect stating their agreement upon all of the following: <br /> .1 The change in the Work; <br /> .2 The amount of the adjustment,if any,in the Contract Sum;and <br /> .3 The extent of the adjustment,if any, in the Contract Time. <br /> § 7.3 CONSTRUCTION CHANGE DIRECTIVES <br /> § 7.3.1 A Construction Change Directive is a written order prepared by the Architect and signed by the Owner and <br /> Architect,directing a change in the Work prior to agreement on adjustment,if any,in the Contract Sum or Contract <br /> Time,or both.The Owner may by Construction Change Directive,without invalidating the Contract,order changes <br /> in the Work within the general scope of the Contract consisting of additions,deletions or other revisions,the <br /> Contract Sum and Contract Time being adjusted accordingly. <br /> § 7.3.2 A Construction Change Directive shall be used in the absence of total agreement on the terms of a Change <br /> Order. <br /> § 7.3.3 If the Construction Change Directive provides for an adjustment to the Contract Sum,the adjustment shall be <br /> based on one of the following methods: <br /> .1 Mutual acceptance of a lump sum properly itemized and supported by sufficient substantiating data to <br /> permit evaluation; <br /> .2 Unit prices stated in the Contract Documents or subsequently agreed upon; <br /> .3 Cost to be determined in a manner agreed upon by the parties and a mutually acceptable fixed or <br /> percentage fee;or <br /> AIA Document A201-—2007.Copyright©1911,1915,1918,1925,1937,1951,1958,1961,1963,1966,1970,1976,1987,1997 and 2007 by The American <br /> Init. Institute of Architects.All rights reserved.WARNING:This AIAx Document is protected by U.S.Copyright Law and International Treaties.Unauthorized 22 <br /> reproduction or distribution of this AIA® Document,or any portion of it,may result in severe civil and criminal penalties,and will be prosecuted to <br /> / the maximum extent possible under the law.This document was produced by AIA software at 15:14:50 on 11/01/2016 under Order No.4982744446_1 which <br /> expires on 07/01/2017,and is not for resale. <br /> User Notes: (2035499384) <br />