.4 As provided in Section 7.3.7.
<br /> § 7.3.4 If unit prices are stated in the Contract Documents or subsequently agreed upon,and if quantities originally
<br /> contemplated are materially changed in a proposed Change Order or Construction Change Directive so that
<br /> application of such unit prices to quantities of Work proposed will cause substantial inequity to the Owner or
<br /> Contractor,the applicable unit prices shall be equitably adjusted.
<br /> § 7.3.5 Upon receipt of a Construction Change Directive,the Contractor shall promptly proceed with the change in
<br /> the Work involved and advise the Architect of the Contractor's agreement or disagreement with the method,if any,
<br /> provided in the Construction Change Directive for determining the proposed adjustment in the Contract Sum or
<br /> Contract Time.
<br /> § 7.3.6 A Construction Change Directive signed by the Contractor indicates the Contractor's agreement therewith,
<br /> including adjustment in Contract Sum and Contract Time or the method for determining them.Such agreement shall
<br /> be effective immediately and shall be recorded as a Change Order.
<br /> § 7.3.7 If the Contractor does not respond promptly or disagrees with the method for adjustment in the Contract
<br /> Sum,the Architect shall determine the method and the adjustment on the basis of reasonable expenditures and
<br /> savings of those performing the Work attributable to the change,including,in case of an increase in the Contract
<br /> Sum,an amount for overhead and profit as set forth in the Agreement,or if no such amount is set forth in the
<br /> Agreement, a reasonable amount.In such case,and also under Section 7.3.3.3,the Contractor shall keep and present,
<br /> in such form as the Architect may prescribe, an itemized accounting together with appropriate supporting data.
<br /> Unless otherwise provided in the Contract Documents,costs for the purposes of this Section 7.3.7 shall be limited to
<br /> the following:
<br /> .1 Costs of labor,including social security,old age and unemployment insurance,fringe benefits
<br /> required by agreement or custom,and workers' compensation insurance;
<br /> .2 Costs of materials, supplies and equipment,including cost of transportation,whether incorporated or
<br /> consumed;
<br /> .3 Rental costs of machinery and equipment,exclusive of hand tools,whether rented from the
<br /> Contractor or others;
<br /> .4 Costs of premiums for all bonds and insurance,permit fees,and sales,use or similar taxes related to
<br /> the Work;and
<br /> .5 Additional costs of supervision and field office personnel directly attributable to the change.
<br /> § 7.3.8 The amount of credit to be allowed by the Contractor to the Owner for a deletion or change that results in a
<br /> net decrease in the Contract Sum shall be actual net cost as confirmed by the Architect.When both additions and
<br /> credits covering related Work or substitutions are involved in a change,the allowance for overhead and profit shall
<br /> be figured on the basis of net increase,if any,with respect to that change.
<br /> § 7.3.9 Pending final determination of the total cost of a Construction Change Directive to the Owner,the Contractor
<br /> may request payment for Work completed under the Construction Change Directive in Applications for Payment.
<br /> The Architect will make an interim determination for purposes of monthly certification for payment for those costs
<br /> and certify for payment the amount that the Architect determines, in the Architect's professional judgment,to be
<br /> reasonably justified. The Architect's interim determination of cost shall adjust the Contract Sum on the same basis
<br /> as a Change Order,subject to the right of either party to disagree and assert a Claim in accordance with Article 15.
<br /> § 7,3.10 When the Owner and Contractor agree with a determination made by the Architect concerning the
<br /> adjustments in the Contract Sum and Contract Time,or otherwise reach agreement upon the adjustments,such
<br /> agreement shall be effective immediately and the Architect will prepare a Change Order.Change Orders may be
<br /> issued for all or any part of a Construction Change Directive.
<br /> § 7.4 MINOR CHANGES IN THE WORK
<br /> The Architect has authority to order minor changes in the Work not involving adjustment in the Contract Sum or
<br /> extension of the Contract Time and not inconsistent with the intent of the Contract Documents.Such changes will be
<br /> effected by written order signed by the Architect and shall be binding on the Owner and Contractor.
<br /> Init. AIA Document A20111—2007.Copyright©1911,1915,1918,1925,1937,1951,1958,1961,1963,1966,1970,1976,1987,1997 and 2007 by The American
<br /> Institute of Architects.All rights reserved.WARNING:This AIA® Document is protected by U.S.Copyright Law and International Treaties.Unauthorized 23
<br /> reproduction or distribution of this AIA® Document,or any portion of it,may result In severe civil and criminal penalties,and will be prosecuted to
<br /> the maximum extent possible under the law.This document was produced by AIA software at 15:14:50 on 11/01/2016 under Order No.4982744446 1 which
<br /> expires on 07/01/2017,and is not for resale.
<br /> User Notes:
<br /> (2035499384)
<br />
|