Laserfiche WebLink
construction cost contingency and a 15% contractor overhead and profit <br /> allowance. <br /> Input: <br /> 1-4.1 Latest plans and specifications <br /> Activities <br /> A-4.1 90% completion of plans <br /> A-4.2 90% completion of specifications <br /> A-4.3 90% completion of opinion of probable construction costs <br /> A-4.4 SRF Application <br /> Products: <br /> P-4.1 90% level plans, specifications, SRF Application package, and opinion of <br /> probable construction costs <br /> TASK 4— ISSUED FOR BID DOCUMENTS <br /> Objective: Provide Final design documents including drawings, specifications, and opinion <br /> of probable construction costs for review and comment. <br /> Approach: Utilizing the latest plans and specifications along with the City's review <br /> comments, AECOM will complete plans and specifications to the 100% level. <br /> The 100% level represents documents that are ready for bidding. The opinion of <br /> probable construction costs will be revised, and remain an AACE Class 1 <br /> estimate with a 10% construction cost contingency and a 15% contractor <br /> overhead and profit allowance. <br /> Input: <br /> 1-5.1 Latest plans and specifications <br /> Activities <br /> A-5.1 100% completion of plans <br /> A-5.2 100% completion of specifications <br /> A-5.3 100% completion of opinion of probable construction costs <br /> Products: <br /> P-5.1 100% level plans, specifications, and opinion of probable construction costs <br /> TASK 5— BID SERVICES <br /> Objective: AECOM will provide bid assistance to the City of Decatur for this project. <br /> Approach: AECOM will utilize the City's review comments to prepare the final plans and <br /> specifications for advertisement and for distribution to prospective bidders. <br /> Approximately 98 Drawings are anticipated. The City of Decatur will arrange for <br /> advertisement in local publication(s). <br /> 4of8 <br />