Laserfiche WebLink
Use of sheeting, shoring and bracing are only as required. This will be clarified in <br />' contract documents. <br /> 5. Is there a geotechnical report for the area of the storm sewer. <br /> Logs of soil borings will be provided. These are for information. Nothing in the contract <br /> documents shall be construed as a guarantee that other materials will not be <br /> encountered or that proportion of materials will not vary from proportions shown on <br /> the logs of test borings. <br /> 6. Section 02324.3.3.1 states "When subsurface materials at bottom of trench are loose or <br /> soft, excavate to greater depth as directed by Engineer until suitable material is <br /> encountered to provide a satisfactory base for pipe installation. Contractor shall remove <br /> and dispose of unsuitable material. Cut out areas of subgrade not capable of compaction <br /> in place. Backfill and compact to 95 percent of Modified Proctor as specified in ASTM <br /> D1557. Will undercutting unsuitable trench bottom and providing CA7 fill be paid for as <br /> an extra cost item? <br /> ' Unsuitable soils encountered will be paid separately during construction via change <br /> order. <br /> ' 7. Can we get access to the west end of the sewer alignment from Dreamland Lake <br /> Drive? Access to the east end of the alignment from W. Eldorado Street. There will be <br /> significant truck traffic hauling in aggregate bedding/backfill as well as off-haul of trench <br /> spoil. For access into the sewer alignment since there will be significant truck traffic, will <br /> we need to install stabilized construction entrance in general accordance with erosion <br /> control standards <br /> Access from Dreamland Lake Dr. is acceptable. Erosion control requirements are a lump <br /> sum item to be based on the Contractor's means and methods. Also, please note <br /> requirement to coordinate with Decatur Park District regarding use of space and <br /> minimization of conflicts with local residents and Park District staff. <br /> 8. Does the City of Decatur have a spoil site for excess trench spoil? <br /> No, hauling and disposal of spoils shall be the responsibility of the Contractor <br /> ' 9. Can suitable topsoil stripped from over the trench area be utilized for placement over <br /> the trench area for the Seeding/ Restoration bid item. Can this topsoil be stockpiled <br /> within the park area, say at the west end of the sewer alignment near Dreamland Lake <br /> Drive. <br /> ' Stockpiling of topsoil is permitted. All disturbed area shall be restored with seeding <br /> following project work. <br />