2. The STATE agrees to pay for all right-of-way, construction and engineering costs subject
<br /> to reimbursement by the CITY, as hereinafter stipulated.
<br /> 3. It is mutually agreed by and between the parties hereto that the estimated cost and cost
<br /> proration for this improvement is as follows:
<br /> STATE CITY TOTAL
<br /> Type of Work Cost % Cost % Total
<br /> All constr. costs $2,281,939 100 $0 0 $2,281,939
<br /> excluding the
<br /> following
<br /> Side Streets
<br /> Mill and $0 0 $10,008 100 $10,008
<br /> resurface
<br /> Resurface $28,865 50 $28,865 50 $57,730
<br /> approaches
<br /> ADA
<br /> Curb Ramps $68,913 80 $17,228 20 $86,141
<br /> Traffic Sienals
<br /> Jasper/Southland $85,328 90 $9,481 10 $94,808
<br /> Lost Bridge $165,970 90 $18,441 10 $184,411
<br /> Rd/S 16th Street
<br /> Special request $0 $1,400 100 $1,400
<br /> paint
<br /> East Riverside $14,498 100 $0 0 $14,498
<br /> Avenue
<br /> E Wood Street $30,100 90 $3,344 10 $33,444
<br /> E Prairie Street $23,058 90 $2,562 10 $25,620
<br /> MLK $4,275 100 VO 0 $4,275.00
<br /> Sub Total $2,702,945 $91,330 $2,790,000
<br /> P&C Engr. 15% $405,442 $13,699 $419,141
<br /> Total $3,108,387 $105,029 $3,213,416
<br /> Participation and reimbursement shall be predicated by the percentages shown above for
<br /> the specified work. Cost shall be determined by multiplying the final quantities times
<br /> contract unit prices plus 15% for construction and preliminary engineering. Participation
<br /> toward the traffic signals shown above shall not exceed $ 50,641 which represents 125% of
<br /> their estimated construction and engineering cost.
<br /> 4. The CITY has passed a resolution appropriating sufficient funds to pay its share of the
<br /> cost for this improvement using form BLR 0911 or the sample attached hereto as
<br /> "Exhibit A" and made a part hereof. ,